Monday 19 May 2025
Reliability boost for passengers in Cornwall following extensive viaduct upgrade
- Region & Route:
- Wales & Western: Western
Passengers will benefit from improved reliability on journeys through Cornwall after Network Rail completed a programme of work to upgrade Ponts Mill viaduct near St Blazey.
Work took place to ensure the 152-year-old viaduct, which carries the Newquay branch line over the River Par, remains safe and reliable long into the future.
As a precaution, a 10mph speed limit has been in place, adding to journey times and meaning trains used extra fuel to slow down to travel over the viaduct and then accelerate after crossing. Temporary repairs were carried out in March 2024, but now, after extensive work to strengthen the structure, the speed restriction has been removed and trains are travelling at line speed of 30mph.
During an extended closure of the railway in March, the timber decks of the bridge were removed and replaced with new steel decks, whilst the bridge girders were also strengthened. The rails, sleepers and ballast (track stone) were also replaced, using two 60-tonne cranes to lift material.
With the bridge now strengthened, trains, including freight from the nearby mineral site, can travel over the viaduct without the need to slow down.
Work now continues to paint the steel on the viaduct and repair the stone of the three columns and two abutments.
Network Rail Programme Manager Dan Parkes said:
“This has been a major programme to not only protect the Newquay branch line but to preserve an historic structure.
“We’re grateful to the local community for their patience while we completed the work.”
ENDS
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - James Crook
Senior Media Relations Manager
Network Rail
07732 644202
james.crook@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk