Monday 13 Jan 2025
Refurbishment of the iconic Hungerford Bridge to begin next week
- Region & Route:
- Southern
- | Southern: Kent
The 161-year old Hungerford railway bridge is to be restored to protect it for the future, with work set to be completed by the end of winter 2028
Starting on 18 January, Network Rail will begin essential work to refurbish the Hungerford Bridge, the structure that takes the railway over the Thames between the South Bank and London Charing Cross station.
The current bridge comprises spans made of wrought iron lattice girders dating from 1864. With such old infrastructure, it’s important that the bridge is maintained so that the railway can be run safely and reliably for passengers.
During the work engineers will prepare and paint the bridge, test the truss pins - which join together the supports – and replace the pin end caps on the girders. All of the original metalwork will be retained and refurbished.
David Davidson, Network Rail’s Kent Route director said: “Many of the bridges on Britain’s railway are from the Victorian era and being responsible for this national heritage is both a privilege and a challenge. Some of the structures are very old, so are vulnerable to corrosion and damage from weather.
“Refurbishment of Hungerford Bridge will take three years, and we won’t need to close the bridge to trains during this first phase as we’ll be working at times that cause the least disruption to train services. This means we are carrying out some of our work during the night.
"To avoid further disruption, we will also use barges to deliver and remove waste materials to Surrey Pier for the period of the works to avoid creating extra traffic and the resulting pollution. This will avoid the equivalent of six truck freight deliveries through central London a week.”
Hungerford Bridge crosses the River Thames from the South Bank, close to London Waterloo station, to the north side of the Thames at Charing Cross Station, east of Trafalgar Square.
It is a steel truss railway bridge flanked by two more recent pedestrian bridges.
The work will start in January 2025 and is expected to be completed by the end of winter 2028.
The refurbishment work will be carried out in two phases, with the first phase commencing on the spans on the Southbank and the south side of the river from January 2025 to January 2026.
The second phase of the works will be the main refurbishment works which will take place on the remaining spans across the river from January 2026 to winter 2028.
There will be additional weekend closures in 2026-2028, with the dates yet to be confirmed.
Notes to Editors
The current bridge uses the original supports (which were later extended by the railway) of the original Hungerford Suspension Footbridge designed by IK Brunel and in use from 1845 to 1860.
The current railway bridge structure was designed by Sir John Hawkshaw and opened to traffic in 1864 (Bridge 7). The bridge was widened in 1886 (Bridge 7A) to form the current structure (7/7A.) Hungerford Bridge has been repaired/refurbished and strengthened throughout its life.
- Strengthening to the cross girders occurred in 1916 and bomb damage was repaired in the 1940’s after the bridge suffered direct hits during the Second World War.
- The most significant work was undertaken between 1978 and 1980 when the decks to Bridge 7 and the Middle Road of Bridge 7A were entirely replaced along with the cantilevered public footway on the eastern side.
- The cantilevered walkway was completely removed around 2002 in connection with the opening of the Golden Jubilee Footbridge structures flanking the railway bridge.
Historic photos of the bridge are available on request.
The railway in Kent and South East London is made up of hundreds of bridges, footbridges and tunnels. Network Rail is investing £213 million to replace or refurbish structures on the route over the next four years.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Paul Prentice
Communications Manager
07354 529345
paul.prentice@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk