Network Rail will shortly begin tree and vegetation management on a 9-mile stretch of the Highland Line.
Work will take place within the railway boundary and on adjacent land between Faskally and Pitagowan from Monday 15 July until the end of March next year.
The work is needed to keep passengers safe and trains punctual and to reduce the risk for lineside neighbours.
Engineers will be working both day and night to clear woody material in a 6m section between the outside rail and the boundary.
They’ll also treat noxious and invasive non-native weeds within the railway corridor while selectively felling and cutting back trees close to the track.
Heritage, landscape and specimen trees will be considered on a case-by-case basis and will be retained where it is safe to do so.
Rochelle McAllister, scheme project manager, Network Rail, said: “We manage thousands of miles of trees and vegetation along the railway to ensure that everything which grows lineside is safe and does not cause delays to trains.
“Through the management of lineside trees and vegetation, we aim to protect the safety of the operational railway line. This keeps passengers safe and reduces risks for lineside neighbours.
“Elements of this work are unavoidably at night for safety reasons however the teams are always mindful of the impact their work may have and do what they can to minimise this. We want to apologise in advance if anyone is disturbed by the work”.
Ahead of the work, environmental surveys have been carried out and the area has been inspected for nesting birds and protected species. We have also worked with our ecologists to minimise the impact of the work on the environment.
Those living closest to the line will be advised about the work by letter with a FAQs section which anticipates and responds to many of the concerns people have raised when we have carried carry out this type of work in other areas.
If anyone has any questions or concerns about this work they can contact Network Rail’s 24hr National helpline on 03457 11 41 41.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk