Railway reopens between Leeds and York after nine days of TRU upgrades completed in North Yorkshire

Region & Route:
Eastern

Major improvement works delivered by the Transpennine Route Upgrade (TRU) in Church Fenton have taken the programme a significant step closer to delivering faster, more frequent and more reliable rail services for customers travelling across the North.

Between Saturday 24 October and Sunday 1 November, engineers worked around the clock to install the new Common Lane railway bridge and complete the fitting of new overhead power lines, allowing faster, greener electric trains on the route in the future.

The previous bridge, built in 1901, was reaching the end of its lifespan. By carrying out the replacement works a year earlier than necessary, TRU has maximised their time accessing the operational railway to modernise infrastructure while also working to prepare the railway for the future installation of overhead line equipment. This means further disruption to the local community will be minimised.

The team didn’t let Storm Boelo stand in its way, with activities rescheduled in advance, enabling work to be temporarily paused for safety during the height of the high winds and poor weather. Teams worked hard to stay on target and the railway re-opened to trains on time.

During the nine-day closure customers were kept on the move through a comprehensive network of replacement bus services to ensure people could get to where they wanted to go.

 

Adam Sellers, TRU senior sponsor, said: 

“We’ve completed this major work at Church Fenton safely and on time, bringing us a step closer to more frequent, faster, greener trains between York, Huddersfield, Leeds and Manchester.

“A big thank you to our teams who worked around the clock and in very challenging weather conditions to deliver this latest milestone.”

 

Carl Harland, TRU Customer Lead for Northern, said:

“We would like to thank our colleagues from across the industry for completing these works at Church Fenton and keeping our customers moving over the past nine days.

“The upgrades that have been delivered form an integral part of transforming the route between Leeds and York, helping better connect our communities. Thank you to our customers for their patience whilst these major upgrades have taken place.”

 

Following the installation of the new bridge at Church Fenton, work has now started to relocate diverted utility services within the new structure, before the road is restored and re-opened in June 2027.

A major programme of improvements was also carried out on the East Coast Main Line in North Yorkshire over the past two weekends, including renewing track and points, upgrading overhead line equipment and drainage, managing vegetation and improving platform infrastructure. The work will help make the railway more reliable and provide smoother journeys for customers.

 

Notes to Editors

TRU fast facts

  • 25% of the route is now electrified, with electric train services now running between Manchester and Stalybridge, and York and Church Fenton
  • Once complete, TRU aims to halve the time lost to delays
  • There are currently 70 worksites across the 70-mile route
  • TRU will deliver:
    • The full electrification of the line
    • Double the number of tracks in key locations, allowing fast trains to overtake stopping services
    • Implement digital signalling to increase speed and capacity
    • Improve all 23 stations on the route, supporting accessibility
  • TRU has over 5000 staff, with 85% coming from within 40 miles of the route – TRU will have created over 8000 jobs across the duration of the programme
  • TRU is expanding freight provision, opening 15 extra freight paths and widening tunnels so shipping containers can travel between ports on the east and west coasts via rail, removing over 1000 lorries a day from the busy roads across the Pennines

Key milestones to date

  • New station built at Mirfield
  • New station built at Morley
  • Introduction of a fully accessible platform 2 at Castleford station to support diverted services between York and Manchester
  • £100m upgrade of diversionary routes completed ahead of major works across the Transpennine Route, increasing railway resilience
  • Upgrade of Hope Valley line complete, with a second platform built at Dore & Totley, as well as 1km of additional track at Bamford to reduce bottlenecks

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Ewan Bayliss
Communications Executive
Network Rail
ewan.bayliss@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk