Railway reopens after East Coast Main line cable fire at Stevenage: Composite of teams fixing signalling cabling at Stevenage-2

Thursday 10 Oct 2024

Railway reopens after East Coast Main line cable fire at Stevenage

Region & Route:
Eastern
| Eastern: East Coast

Rail passengers are being thanked for their patience after a fire at Stevenage disabled signalling for trains on the East Coast Main Line.

A blaze beside the railway was first reported by a train driver at 12.30pm yesterday (Wednesday 9 October) with Hertfordshire Fire and Rescue Service putting out the flames by 2pm.

Fibre-optic cables suffered significant damage and brought major disruption to trains in and out of London King's Cross.

Network Rail engineers worked throughout the night to restore railway signalling with the majority of trains running on the East Coast Main Line as normal this morning.

However, teams needed longer to repair the cabling which controls signals between Gordon Hill and Stevenage.

Shortly after 2pm today (Thursday 10 October), engineers finished their work to allow that route to reopen for Thameslink and Great Northern rail services.

Passengers are still being encouraged to check National Rail Enquiries for the latest travel information as timetables return to normal.

Photos have been released today showing the burned signalling cabling and equipment and the efforts made to repair the infrastructure.

The fire damaged 25 individual telecommunications and signalling cables along a 20-metre-long section of railway.

Over the last 24 hours teams have raced to carry out temporary repairs to prioritise getting trains running again for passengers and freight.

Work will continue over the weekend to renew the protective casing the cables sit in - known as troughing - which was also badly damaged in the blaze.

This won't impact train services and will be carried out to cause minimum disruption to passengers.

When that work is expected to finish on Monday, it's estimated that more than 1,000 metres of cable will have been replaced in total.

Paul Rutter, Network Rail’s East Coast route director, said: “I’d like to thank passengers for their patience after many had really challenging journeys due to the major signalling fire in Stevenage which badly damaged fibre-optic cabling yesterday.

“Our engineers have now carried out repairs so the signalling systems are working for trains to run again on all routes. While timetables get back to normal we’d advise people to check National Rail Enquiries for the latest travel information.”

It’s not yet clear how the fire started, with investigations ongoing into the cause.

To plan journeys in advance people should visit www.nationalrail.co.uk.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Chris Halpin
07740 782954
chris.halpin@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk