Railway line between East Grinstead and Lingfield to reopen by Monday 30 March: Cookspond

Monday 24 Feb 2020

Railway line between East Grinstead and Lingfield to reopen by Monday 30 March

Region & Route:
Southern

Work is underway to reopen the railway between East Grinstead and Lingfield by 30 March after two landslips blocked the line.

There have been two landslips between Dormans and East Grinstead, where the railway lies between a remote woodland, south of Wilderness Lake.

The first landslip happened on 28 December, but we were able to continue running trains with a speed restriction. Network Rail engineers began working on a plan to shore up the line, but Storms Ciara and Dennis damaged the embankment even more and we had to close the line for safety reasons.

Works to repair the slip involve building an 800-metre-long road just to reach the site, due to its remote location. Steel beams will be driven into the ground to build a wall to repair the embankment, and Network Rail engineers will be using a range of equipment including cranes and road-rail vehicles.

Almost 25,000 tonnes of new material needs to be brought in to replace the soil lost in the slips and will be delivered to site on 25 separate trains. Once the railway is open to trains, more work will be done to shore up the section in between the two landslips when it is less disruptive to passengers.

Shaun King, route director for Sussex said:

“I really appreciate how passengers are having their journeys affected by this landslip. I want to assure them we are challenging each other and reviewing our plans constantly to see if we can get this railway open at the earliest opportunity before 30 March.

“I really appreciate everyone’s patience while we do this work.”

Southern Customer Services Director, Chris Fowler said:

"We understand the difficulties our passengers are facing due to this landslip and we're doing our very best to keep people moving during the closure.

"We have additional car parking at Lingfield and Gatwick Airport, rail replacement bus services from East Grinstead to Three Bridges and Lingfield, and our tickets are being accepted on many local buses and other train services.

"For full details, please visit our website www.southernrailway.com."

Two trains per hour are running between Lingfield and London Victoria and during peak times, three 12-car Thameslink trains between Oxted and London Bridge are running. Rail replacement bus services are also in place between Hurst Green and East Grinstead.

Please continue to check before you travel and for further updates, visit www.southernrailway.com and www.thameslinkrailway.com   

Notes to Editors

Climate change could increase the frequency and severity of extreme weather and we are planning now in order to provide a safe, reliable network in the future. Over the last decade, summers have been 13% wetter and winters have been 12% wetter than the period 1961-1990.

Six of the ten wettest years have occurred since 1998 in a UK series stretching back to 1862. Eight of the ten warmest years for near-coast UK sea-surface temperatures have also occurred this century.

To combat this change, we are working closely with governmental and specialist organisations to prepare our railway for the climate changes projected over the next few years, decades and beyond.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Leonard Bennett
Leonard.Bennett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk