Monday 19 Apr 2021
Railway improvements close Euston station this May bank holiday
- Region & Route:
- North West & Central
- | North West & Central: West Coast Mainline South
- Railway improvements at Euston, Milton Keynes and Watford mean changes to West Coast main line journeys
- London Euston railway station will be closed between 1-3 May - trains will start and finish at Milton Keynes
- Passengers are advised to travel either side of the bank holiday on Friday 30 April and Tuesday 4 May
- People should follow Government guidance and minimise the number of journeys they make where possible
Rail passengers are being urged to travel either side of the early May bank holiday when hundreds of railway engineers improve the West Coast main line.
Millions of pounds is being invested to improve future journeys for passengers and freight on Network Rail’s West Coast South route.
Between Saturday 1 and Monday 3 May, Euston station will be closed to main line train services* while track upgrades take place in London, Watford and Milton Keynes.
The best time to travel will be on Friday 30 April and Tuesday 4 May.
Passengers needing to travel on the days in between will have longer journeys, fewer available seats, and may need to use rail replacement buses.
People should continue to follow Government guidance around the use of public transport and minimise the number of journeys they make where possible.
Those needing to travel during the railway improvements should plan ahead by visiting: www.nationalrail.co.uk/westcoast
James Dean, Network Rail’s West Coast South route director, said: “There is never an ideal time to shut the railway and we have worked hard to minimise disruption across the spring and summer – including moving work over the Easter and Spring bank holidays.
“It is fantastic to see more passengers return to the railway and we want to make journeys as easy as possible for those travelling over bank holidays. We are carefully balancing that with the need to carry out essential railway improvements and maintenance to provide a safe and reliable railway for the future.
“The scale of work planned this May will mean changes for passengers, but we’re working with train companies to minimise disruption to people as much as possible.”
Elsewhere in Network Rail’s North West and Central region, further essential work taking place between 1-3 May includes:
- Track upgrades take place at various locations between Preston – Penrith
- Signalling upgrades continue in Trafford, Manchester.
- Work at Euston station to prepare it for HS2, Britain’s new high-speed railway.
The early May bank holiday will also be a major milestone for the East West Rail project - as work continues to reinstate a rail route between Oxford and Bletchley for the first time in more than 50 years.
Huge steel beams will be lifted across all four lines of the West Coast main line as a flyover is rebuilt. It involves the dismantling of the 25,000 volt overhead line system which powers electric trains.
Robert Nisbet, director of nations and regions at the Rail Delivery Group, said: “Rail staff will be working hard to upgrade the network over the May bank holiday to make future journeys more reliable, so we’re asking anyone travelling between 1 and 3 May to check before they travel.
"While extra cleaning and better information will help people travel with confidence, we ask passengers to wear their face masks and to consider whether their journey is really necessary if it will be affected by engineering work.”
This spring Network Rail brought forward some planned bank holiday projects and did the work while fewer people were travelling during the national coronavirus lockdown.
This included carrying out projects in record breaking time in North London and Northamptonshire, saving taxpayers millions of pounds.
- Rapid railway renewals on West Coast main line in North London
- Super-fast Northampton railway upgrades complete for passengers
This super-fast approach meant Euston would not need to close at Easter or the late May bank holiday.
However, the scale of the upgrades further up the West Coast main line meant the closure over 1-3 May was unavoidable.
Reviews into other planned summer upgrade work is underway to reduce its impact on passengers as the country emerges from the coronavirus pandemic.
For more information visit www.nationalrail.co.uk.
Notes to Editors
For interview requests please contact media manager Chris Halpin on 07740 782 954 or email chris.halpin@networkrail.co.uk
*Only Caledonian Sleeper services will run in/out of Euston over early May bank holiday.
Euston preparation work for HS2
Preparatory work on the approach lines at Euston to enable HS2 will be carried out over a number of weekends, resulting in platform and service alterations, including some being reduced between April and August.
For Euston to be the London terminus for HS2 - two of the approach lines to the station, will be closed for a combined total of 12 weeks this spring/summer. This will be split into two separate six-week closures:
- 02 April to 17 May 2021
- 17 July to 31 August 2021
Most services into and out of Euston will run during the work on the approach lines to prepare the way for high speed rails.
However, over the early May bank holiday weekend, no trains will run in or out of London Euston station, affecting journeys south of Milton Keynes.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk