Railway between Southampton and Bournemouth to close for 5 days for major improvements in November: View of upgraded track at Bristol East Junction

Monday 6 Sep 2021

Railway between Southampton and Bournemouth to close for 5 days for major improvements in November

Region & Route:
Southern: Wessex
| Southern

The railway between Southampton and Bournemouth will close for five days from Monday 1 to Friday 5 November to deliver a range of long-term improvements making journeys more reliable and resilient to extreme weather.

Engineers will upgrade the track, signals and drainage between Totton and Bournemouth, removing speed restrictions and making South Western Railway and Cross Country journeys through the area faster.

Mark Killick, Network Rail Wessex route director, said: “This critical improvement work will improve journeys, making them more resilient and allowing us to remove speed restrictions.

“To support the country building back from the pandemic and as a reflection of a rise in leisure and tourism travellers to the South Coast, this critical work will be completed over five weekdays rather than closing the railway for a number of weekends.

"Changing travel patterns mean our railway is busier at weekends than midweek and it’s important for us to minimise the number of people affected by the work being carried out. We never take the decision to close a busy stretch of railway lightly and have reviewed our approach carefully to confirm it is the best option.

“We are working with operators SWR and Cross Country to plan alternative travel arrangements and I would encourage anyone travelling that week to check before they make their plans.”

Alan Penlington, SWR’s customer experience director, said: “The work Network Rail are carrying out from the 1 November will mean big improvements for our customers. Not just a more reliable and resilient service, but also visible improvements.

“I realise these works will mean significant disruption for our customers and I’d like to remind anyone who’s traveling to plan ahead to see if their journey is affected. Replacement buses will be in operation meaning journeys will take longer. I’d like to thank customers for their patience and understanding whilst these essential works are carried out.”

Over the five days, engineers will work at several locations carrying out:

  • Track level improvements at Brockenhurst, Sway and Hinton Admiral
  • Drainage improvements in the Sway area to help reduce delays and cancellations during extreme weather
  • Bridge maintenance in the Christchurch area to ensure structures can support track and trains for years to come
  • Track and signalling maintenance at Totton, Beaulieu Road, Brockenhurst and Christchurch
  • Installation of new rails between Hinton Admiral and Christchurch and new ballast and sleepers at Sway to improve reliability.

Notes to editors

Travel information

Monday 1 November

  • Buses will replace South Western Railway (SWR) services between Southampton Central and Bournemouth and between Brockenhurst and Lymington Pier
  • CrossCountry services between Bournemouth and Manchester Piccadilly will terminate at Southampton Central, with buses replacing trains from both Southampton Airport Parkway and Southampton Central to Bournemouth
  • Please note, buses will not call at Beaulieu Road

Tuesday 2 – Friday 5 November

  • SWR services between London Waterloo and Weymouth will terminate at Brockenhurst with buses providing onward travel to Bournemouth
  • SWR services between London Waterloo and Poole will terminate at Southampton Central with buses providing onward travel to Brockenhurst and Bournemouth
  • CrossCountry services between Bournemouth and Manchester Piccadilly will terminate at Southampton Central, with buses replacing trains from both Southampton Airport Parkway and Southampton Central to Bournemouth

 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Martin Spencer
Martin.Spencer2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk