Rail passengers thanked for their patience after Ashford line landslip prevention works carried out: Bearsted Complete (4)

Monday 16 Aug 2021

Rail passengers thanked for their patience after Ashford line landslip prevention works carried out

Region & Route:
Southern: Kent
| Southern

After a nine-day line closure while £10m of major improvement work took place, the railway between Maidstone East and Ashford International reopened to passengers this morning (Monday).

Network Rail and contractors BAM have been repairing and reinforcing the steep sides of a cutting near Bearsted, which was prone to landslips and rock falls. A rock fall even took place while the work was ongoing, underlying the importance of the project.

In addition, Network Rail used the time the line was closed to carry out essential maintenance, such as painting, at stations along the line and to improve the electrical supply to trains along the route, laying new cables.

Network Rail’s route director for Kent, Fiona Taylor, said: “This was a massive job for us and for our neighbours and passengers and we really appreciate their patience. The section of line between Maidstone East and Bearsted was a big worry, with two rock falls in recent years and another one last week. The work we’ve done over the past nine days has helped make it much safer.

“We don’t get to close railways very often, so we took advantage of the time to do lots of other work, from laying new cables to painting bridges, railings and roofs, and even jet washing platforms.

“We’ve got a bit more to do in the coming weeks, so our neighbours will still see us around, but passengers will be pleased to hear that trains are running again”.

Southeastern Train Services Director, Scott Brightwell,  said: “I want to say a big thank you to all our passengers for bearing with us while this essential repair work was carried out.

"Reducing the risk of landslips across our network is an important part of providing a reliable service. We also took the opportunity to make some station improvements while the line was closed and I hope our customers are pleased with what they see.”

The work at Bearsted involved drilling soil and rock nails deep into the ground on either side of the line, and pumping grout around them to hold the sides of the cutting together.

Netting will be laid along the top to hold looser material in place and stop the risk of rock and soil being washed onto the railway in heavy rain.

During the works engineers installed 1,100 rock bolts and 500 nails into the cutting and drilled a total of 6,800 metres of bolt holes.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Scott Wilson
Media Manager
Network Rail
07395 389658
scott.wilson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk