Putting it to the test: Changes on Northern City Line as East Coast Digital Programme tests and commissions new equipment: Putting it to the test Changes on Northern City Line as East Coast Digital Programme tests and commissions new equipment

Monday 28 Mar 2022

Putting it to the test: Changes on Northern City Line as East Coast Digital Programme tests and commissions new equipment

Region & Route:
Eastern: East Coast
| Eastern
  • Testing and commissioning of new signalling equipment takes place in April and May
  • Changes to services between Finsbury Park and Moorgate 
  • Passengers urged to plan their journeys ahead of time

Passengers travelling on the Northern City Line in April and May are being urged to plan ahead as work to test and commission newly installed signalling equipment takes place.

This work will take place on 9/10 April and the Early May Bank Holiday weekend (30 April to 2 May inclusive). The first weekend will see the new equipment rigorously tested ahead of it being commissioned over the Bank Holiday weekend.

The work is part of the East Coast Digital Programme, which will see the introduction of digital signalling on the Northern City Line, which runs between Moorgate and Finsbury Park.

The upgrade to the route will enable signallers to communicate with the latest in-cab technology on trains. Being able to respond in real time will boost reliability and reduce delays, creating a more modern and reliable railway for passengers.

The upcoming work can only take place safely when no passengers services are running. So, on the above dates, no service between Finsbury Park and Moorgate will be available. Instead, trains to and from Moorgate will be diverted into London King’s Cross.

Passengers are advised to allow plenty of time for their journey and check before travelling via National Rail Enquires or greatnorthernrail.com

Toufic Machnouk, Network Rail’s Director, Industry Partnership Digital, said: “This is an important step forward on the East Coast Digital Programme as it brings us closer to delivering more reliable journeys on this route.

“Testing and commissioning the new equipment is a key part of this upgrade, but it does mean changes to services in April and May. We’re sorry for any inconvenience which this causes and we’d encourage passengers to check their journey ahead of time.”

Jenny Saunders, Customer Services Director for Thameslink and Great Northern, said: “While Moorgate trains are diverted to King’s Cross, customers can use their tickets on London Underground between the two terminals.

“We thank our passengers for their understanding while Network Rail takes the next big step in creating a modern, more reliable railway on this important route. People returning to rail travel can be confident that we continue to treat all our trains and stations regularly with a powerful virucide for long-lasting protection.”

ENDS

Notes to Eds

When trains are diverted from Finsbury Park to London King’s Cross, passengers will be able to use their ticket on London Bus route 271 and on London Underground between London King's Cross / London St Pancras International and Moorgate.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Amy Brenndorfer
Senior Communications Manager
07858375508
07730359569
Amy.Brenndorfer@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk