Platform removal clears way for double tracking at Cameron Bridge: Cameron Bridge Platform spoil-2

Tuesday 27 Sep 2022

Platform removal clears way for double tracking at Cameron Bridge

Region & Route:
Scotland’s Railway: Scotland

Work to demolish the old station platforms at Cameron Bridge is now complete.

Following the successful completion of the first mile in March, and significant progress on the second mile, the removal of the old platforms of the former Cameron Bridge station clears the way for the next stages of track work.

The old platforms adjacent to the Diageo factory were 210 metres in length and made up from masonry and fill materials totalling approximately 5000 tonnes. Their removal was needed to clear the way for the double track railway which will reconnect Leven to the mainline rail network.

The demolished platform material will be retained onsite and fittingly, will be used as infill for the new Cameron bridge station platforms which is being built 200 metres to the east.

Local people in the Cameron Bridge area are being offered the opportunity to see the final plans for the station in advance of them being submitted for planning consideration at one of two community drop-ins from 4pm-7pm on Monday 3rd October at the Methilhill Bowling Club, Main Street, Methilhill, KY8 2DP

The size and scale of the work to remove the platforms and the plant and machinery now operating on the construction of the Rail link project offer further evidence of the dangers to those who are still using the railway corridor for leisure purposes.

The project team is keen to reiterate the message that local people should not now be using the area for their own safety to avoid coming into contact with engineering trains, railway plant and machinery delivering the work.

Joe Mulvenna, Project Manager for the Levenmouth Rail Link Project said:

“The platform demolitions offer further evidence of the progress now being made on the delivery of the project.

“Work is ongoing all across the route and activity is set to ramp-up even further in the coming months and so we are asking people who have previously used the area to walk dogs, for leisure or for exercise to please find an alternative.

“Increased work activity means more vehicle movements and the first-mile section is now a live railway and so very dangerous.  Our priority is safety, both of the local people and for those working hard to deliver the project, and the best way to promote safety is by now asking local people not to continue to use the railway corridor.”

Notes to Editors

Following successful completion of a range of preparatory activities the project to deliver the new Levenmouth Rail kicked off in March 2022.

Work includes:

  • 19 single track kilometres of new / reinstated railway. (Fully double tracked railway)
  • Two new modern accessible stations
  • Electrification of the line
  • Work with partners to optimise interchange options connecting stations
  • Opportunities in freight and tourist/charter connections

The investment value of the project is £116.6m

The programme is scheduled to complete in Spring 2024

Current Status:  

Work to upgrade Thornton North Junction was completed during a line closure on Sunday 6th March.  This enabled the connection onto what will be the Levenmouth branch line.

The project has completed the first mile of track, which has now been commissioned and being used to support construction of the subsequent phases of work on the project

Current work to the west of the route includes fencing, re-profiling of embankments, drainage and cabling and track works.  Bridge works are ongoing along the length of the rail corridor. 

  • It is anticipated that Station designs will be complete and planning applications made in October 2022
  • Diversion of utilities has started on the Leven bridge and it is anticipated that preparatory work on the (Bawbee) Leven bridge will get underway in October/November to prepare for closing the road in early 2023.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk