First planning permission submitted by Network Rail to upgrade London Waterloo station: London Waterloo station

Monday 27 Jul 2015

First planning permission submitted by Network Rail to upgrade London Waterloo station

Region & Route:
| Southern

The multi-million pound improvement and expansion of London Waterloo has moved an important step closer this week as a planning application for works to enable more trains to run in and out of the station has been submitted.

London Waterloo is already Britain’s busiest station, with almost 100m passengers a year and a train arriving and departing every minute at the busiest times of day. With numbers forecast to grow by 40% over the next 30 years, Network Rail and South West Trains are working together to bring the platforms in the former Waterloo International Terminal back into use so more trains can run.

These will be the first major changes to Waterloo since the 1930's, providing five new platforms for London commuter services and completely redesigning the concourse and platforms to be suitable for the hundreds of thousands of passengers passing through every day.

The first part of this project involves strengthening three bridges on the approach to platforms 20-24 as well as changing the layout of the track and platforms. If the planning application is approved, work on the bridges is expected to start in October and is scheduled to be completed by the end of 2016.

A comprehensive public awareness programme is now underway, with letters and leaflets being sent to local homes and businesses to explain the proposals. There is also further information online at www.networkrail.co.uk/wcip as well as contact information to help residents and businesses get in touch and ask further questions.

John Halsall, route infrastructure director for Network Rail, said: “The project to improve the railway and strengthen the bridges on the approach to Waterloo is an absolutely vital part of our plans to improve capacity at Britain’s busiest station.

“The submission of the planning application to carry out this work is an important step forward and, if approved, we expect to start work before the end of the year.”

Tim Shoveller, managing director of South West Trains, added: “We operate one of the busiest railways in Europe, with over half a million passenger journeys every day.

“The biggest investment for decades on our network is well underway but the work to expand London Waterloo is absolutely vital to make sure we can provide much needed extra space, both for our customers now and in the future."

The planning application for the proposed work has been submitted to the London Borough of Lambeth. If permission is granted preparation work would be expected to start in October 2015, with construction taking place between November 2015 and the end of 2016.  Associated track and signalling work will then continue until mid-2017.

Where possible, work will take place during normal working hours, Monday to Friday (8am-6pm). However, there will be some cases where work will need to take place on Saturday mornings and overnight. This will be clearly communicated to neighbours.

A number of temporary road and footpath closures are likely to be required and if so clear signs will identify alternative routes. If planning consent is granted, the exact locations and times of these temporary closures will be published as part of the detailed design work.

The proposed works are a vital part of the overall programme to increase capacity at London Waterloo and ensure it can continue to provide for the growing number of passengers using the station. Strengthening the bridges will allow platforms 20-24, currently part of the former Waterloo International Terminal, to be used for domestic services.

In addition, plans are also being developed to extend platforms 1-4, to allow 10-car trains to run on the Suburban network for the first time. Meanwhile, more than 250 additional train carriages are being introduced on to the network. Combined, this will provide a 30% increase in capacity across the network, the biggest increase in capacity for decades on one of Britain’s busiest commuter networks.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
James Banks
Media Relations Manager
Network Rail
033 0854 3836
07710 961064
james.banks@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk