Latest on repair plan to get Kirkby station reopen for passengers: Recovery team getting derailed Merseyrail train back onto the track at Kirkby station

Wednesday 17 Mar 2021

Latest on repair plan to get Kirkby station reopen for passengers

Region & Route:
North West & Central
| North West & Central: North West

Work is taking place to get Kirkby station in Liverpool reopened to passengers as soon as possible after an incident involving a Merseyrail train.

The 6.35pm service from Liverpool to Kirkby ran through the buffer stop on Saturday 13 March and left the track at the end of the line.

Over recent days the rear carriages of the train have been taken away from the station.

The front carriage which ran through the buffer stop is taking longer as its wheels could be damaged. This means it needs to be removed by a specialist recovery locomotive.

Video release today (17 March) shows the damaged Merseyrail train slowly being pulled back onto rails yesterday evening.

Once it is out of the station Network Rail engineers will be able to properly assess damage to track, the platform surface and signalling system and set out the repair plan.

The best case scenario would see Merseyrail trains running again from the middle of next week, and Northern services from Monday 29 March.*

Phil James, route director for Network Rail’s north west route, said: “Following Saturday’s incident in Kirkby, we’re working with Merseyrail and Northern to reopen the station as quickly as possible to passengers.

“This is complex recovery and repair job and I’d like to thank passengers for their patience. I'd urge anyone who needs to travel to or from Kirkby to check with their train operator for the latest information.”

Andy Heath, managing director at Merseyrail, said: “We are working closely with our partners at Network Rail to reopen Kirkby station as soon as possible following Saturday evening’s incident and understand the inconvenience this has placed on our passengers.

“I would like to remind passengers that if they wish to travel to Fazakerley or Kirkby they should board Ormskirk services to Aintree where a rail replacement bus service is in operation calling at Fazakerley and Kirkby stations.”

Chris Jackson, regional director at Northern, said: “We’re working closely with colleagues across the rail industry to keep our customers on the move and we’re grateful to Network Rail for their efforts in helping to reopen Kirkby as soon as possible.

“In the meantime, our customers can continue to travel between Kirkby and Wigan, though we are operating buses between Kirkby and Rainford while the repair work is carried out.”

The ongoing repairs means both Northern and Merseyrail services are unable to serve Kirkby station with rail replacement buses in operation to keep people on the move.

For the latest developments Merseyrail passengers can check www.merseyrail.org/kirkby-line-latest-update.

Investigations are continuing into the cause of the derailment and the Rail Accident Investigations Branch will report its findings in due course.

Passengers who need to travel should continue to follow government Covid-19 guidance when using public transport and check before they travel at www.nationalrail.co.uk.

Notes to Editors

*The railway line at Kirkby station is effectively split in two - one half serving Merseyrail to the west and the other serving Northern to the east.

The buffer stop separates Merseyrail's electrified track from Northern's non-electrified track.

Because the train ran through the buffer stop it damaged the track on which Northern's diesel services run and that will take longer to repair.

It's estimated Northern services will be able to serve Kirkby again from Monday 29 March.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail