Passengers thanked after West Coast main line reopens following emergency landslip repairs: Church Lawford Landslip 2

Tuesday 13 Feb 2024

Passengers thanked after West Coast main line reopens following emergency landslip repairs

Region & Route:
North West & Central: West Coast Mainline South

Network Rail has thanked passengers after completing major repairs to stabilise a railway embankment on the West Coast main line after storms and heavy rain caused a landslip between Coventry and Rugby on Sunday (11 February).  

The railway between London Euston and Birmingham reopened this afternoon (Tuesday 13 February) after rail engineers closed the line to secure the embankment allowing trains to safely resume. 

Overnight on Monday (12 February) until lunchtime Tuesday (13 February) over 800 tonnes of soil was excavated and transported away from site by rail.  

On Sunday (11 February) soil moved from the embankment onto the track near the village of Church Lawford after persistent heavy rainfall weakened the earth beneath it. 

Although the landslip affected only one of two tracks, engineers needed to close the line entirely to safely repair and fully reopen the West Coast main line for passengers and freight services. 

Network Rail has worked round-the-clock with its contractor Murphy to remove vegetation from the embankment before excavating soil away from the track.  

Close monitoring continues and work is currently being planned to further stabilise the railway embankment which will be delivered in overnight closures to limit the disruption to passengers.  

James Dean, route director for Network Rail, said: “I’m sorry to passengers who’ve been affected by the closure of the West Coast main line while we completed emergency repairs to the landslip between Coventry and Rugby.  

“I’m pleased to advise that we’ve reopened both tracks this afternoon – with a reduced speed limit – which means passenger and freight trains can run again.  

“I want to thank passengers for their patience and ask those travelling to check www.nationalrail.co.uk for the latest journey information.” 

Jonny Wiseman, LNR customer experience director, said “Safety on the railway is paramount and I would like to thank our passengers for their patience while Network Rail completed this important lineside earthwork. 

“With the line now fully reopened our services between Birmingham New Street and London Euston can return to the usual timetable and we look forward to welcoming passengers back on board.” 

Dave Whitehouse, Safety and Security Director at Avanti West Coast, said: “Although the emergency engineering work is now completed, trains will still be disrupted between London and Birmingham for the remainder of the day whilst we work to resume services fully for tomorrow.     

“The advice is to check before you travel, using our websites or social media. We would to like to thank customers for their patience during this time.” 

For safety reasons trains will run at a reduced speed on the affected section of track while engineers monitor the embankment and complete further overnight repairs. 

Passengers should check www.nationalrail.co.uk for the latest travel advice.  

Notes to Editors

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk