Passengers thanked after rail freight interchange connected to main line: People on track sun image copy at Northampton interchange

Monday 11 Sep 2023

Passengers thanked after rail freight interchange connected to main line

Region & Route:
North West & Central
| North West & Central: West Coast Mainline South

Rail passengers are being thanked after major work to connect a new rail to road freight interchange with the West Coast main line.

For the last nine days, Network Rail engineers have worked day and night to allow future freight trains to travel from one of Europe’s busiest mixed-use passenger and freight routes to the new SEGRO logistics park in Northampton.

The work has seen new track, points and signalling systems installed to connect the existing railway to the new sidings at the under-construction freight facility.

When complete next year, it will provide 5 million square ft of warehouse space and employ up to 7,000 people.

The new railway connection, which will be used by freight company Maritime, will see thousands of tonnes of goods switch between rail and road beside Junction 15 of the M1 motorway every day.

Once operational, four freight trains will serve the new Northampton interchange each day - with the capacity for more in future.

Each freight train takes up to 76 heavy good vehicles off the road, making it a much greener way to transport economically important goods around the country.

Today (Monday 11 September) Network Rail has thanked passengers for their patience during the essential work which has seen some changes to journeys.

James Dean, Network Rail's West Coast South route director, said: “Connecting this new freight interchange to the mainline railway network is a huge milestone and shows our commitment to working with freight operators to moving more goods in the most environmentally friendly way possible – by rail.

“We know this work has meant longer journeys for passengers over the last nine days, so I’d like to thank everyone impacted for bearing with us while we carried out this important work which will benefit both the environment and the economy in future.”

Jonny Wiseman, London Northwestern Railway customer experience director, said: “I would like to thank passengers for their patience while these important engineering works were completed. Services on the West Coast main line are now running to our normal timetable.”

Barry Milsom, Avanti West Coast executive director of operations and safety, said: “We would like to thank customers for their patience over the last nine days while Network Rail carried out this important work, which will boost sustainable transport opportunities for freight on the West Coast Main Line.”

The West Coast Main Line is one of the busiest freight routes in Europe carrying 40% of all UK rail freight traffic.

Further work will now take place with freight operators and developers with the interchange expected to be operational in 2024.

John Williams, Maritime executive chairman, said: “These developments, at SEGRO Logistics Park Northampton are important, long-term commitments for Maritime to reduce our environmental footprint by developing a network of low carbon, strategic freight connections across the country to promote modal shift from road to rail for container transport and for domestic distribution, with local distribution by electric-powered trucks.

“Building and operating modern, inland rail freight interchanges, supported by the largest dedicated fleet of vehicles in the country, enables us to deliver terminal to terminal rail solutions and highly efficient rail to door and door to rail services for our customers who are looking for long term, supply chain protection and sustainable transport solutions.”

For more information on Network Rail’s freight operations you can visit: https://www.networkrail.co.uk/industry-and-commercial/rail-freight/

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk