PASSENGERS GET A TICKET TO RIDE ON A 21ST CENTURY RAILWAY INTO SOUTH WALES: Engineers working round the clock to complete improvement work in South Wales

Monday 4 Jan 2010

PASSENGERS GET A TICKET TO RIDE ON A 21ST CENTURY RAILWAY INTO SOUTH WALES

Region & Route:
| Wales & Western: Wales & Borders
| Wales & Western


Engineers working round the clock to complete improvement work in South Wales  Severn Tunnel Junction revamped during the first phase of £150m re-signalling work in Newport


Today marks the successful completion of the first phase of improvement work for the  huge rail investment scheme in the Newport area, which will enhance the reliability of the 3m rail journeys made each year via Severn Tunnel Junction.


The improvement work, carried out over the Christmas and new year holiday period, is part of the £150m Newport area re-signalling scheme to usher in a 21st century railway to south Wales.  More than 400 engineers worked round the clock every day, ploughing in nearly 100,000 manhours altogether to complete the work on time. 

Chris Rayner, route director for Network Rail, said: "Network Rail has delivered on the day we said we would for an extremely complex programme of work.  This first phase of work alone took nearly four years to bring it from canvas to concrete and the result today is because of the hard work from our engineers and all our partners pulling in to make it possible. 

"Severn Tunnel Junction is among the busiest railway junction in Wales and a key link to England, it is now even more robust to serve passengers in the many decades to come. We have made good on decades of underinvestment, and this effort in south Wales will continue to meet growing rail demand."

The second phase of this scheme, which will include the re-signalling of Newport Station and re-modelling of the track layout at Maindee Junction, has already started and work is due to complete by the end of the year. 

The majority of the work will be carried out overnight when trains are not running to minimise any passenger disruptions.

The railway at Severn Tunnel Junction is now completely revamped with a new layout that removes the bottleneck in the area, which will cut delays and promise the capability for more trains to run in the future.

For the first time in 25 years, passengers travelling to England will embark from the newly restored  platform 4 that was abandoned during the 1980s. 

The new signalling centre in Cardiff also swings into operation for the first time today as cutting-edge digital technology is used to manage train operations between East Usk (Newport) and Pilning (Bristol).   

A total of 81 signals, 10 new signal gantries, 168 train detection counters and 39km of power cable have also been renewed between Pilning (Bristol) and East Usk.  The upgrade will extend the lifespan of the rail infrastructure for at least another four decades.

Passengers will also benefit from new waiting shelters and digitised real-time information system at the station as part of a separate initiative, jointly funded by Network Rail, Arriva Train Wales, Welsh Assembly Government and SEWTA.

The railway around Severn Tunnel Junction suffered years of decline after it was bombed in World War II, this scheme has reversed the history of Severn Tunnel Junction. 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk