Passengers advised of West Coast main line and Euston HS2 upgrades in 2021: Euston track work 16x9

Thursday 19 Nov 2020

Passengers advised of West Coast main line and Euston HS2 upgrades in 2021

Region & Route:
North West & Central
| North West & Central: West Coast Mainline South

Network Rail has announced major upgrades on the West Coast main line and at London Euston in spring/summer 2021.

The work, part of Britain’s Railway Upgrade Plan and HS2 Phase One*, will make passengers’ journeys more reliable and ease pressure on the West Coast main line by adding more railway capacity. 

Though passenger demand is reduced due to the coronavirus pandemic, the rail industry is planning for an increase in passenger numbers next year.

The work has been announced early to give passengers plenty of notice so they can make informed choices when travelling over spring/summer.

Two lines into Euston station will be taken out of service for two six-week periods – 2 April to 17 May and 17 July to 31 August – to enable the new HS2 terminus to be built. Weekend work will also take place between April and the end of August.

Most train services will continue running while this work takes place, but there will be some timetable and platform alterations. 

Other essential rail upgrades are planned over the Easter, Early May, Spring and August bank holiday weekends, which in 2021 fall on:

  • 2 – 5 April (Easter bank holiday)
  • 1-3 May (Early May bank holiday)
  • 29 -31 (Late May bank holiday)
  • 28-30 August (Summer bank holiday)

This includes:

  • Major track renewals between Rugby – Birmingham, Crewe – Warrington, Preston – Lancaster and Carstairs – Carlisle 
  • Further Bletchley flyover work as part of the East-West Rail project

This means stations and trains between Euston and Scotland may be busier, services will change, journeys may take longer and in some instances buses will replace trains.

James Dean, Network Rail’s West Coast South route director, said: “Our work will make the West Coast main line more reliable for our passengers and pave the way for HS2, which will bring much-needed extra railway capacity.

“There is no question such large scale improvements will mean changes for passengers, but we’re working with the industry to minimise disruption to passengers as much as possible next year.

“We’re letting people know many months in advance so none of this comes as a surprise and passengers can stay on the move while we do this vital work.”

Patrick Cawley, director of On Network Works for HS2 Ltd and Network Rail said: “Investing in HS2 will create additional rail capacity across the existing UK network, providing more local, regional and intercity services. Although some disruption to the current rail service is unavoidable in the short term, in preparation for this we have completed other service upgrades to minimise impact, such as increasing platform lengths at busy stations on the West Coast main line.”

The rail industry has worked closely to combine the Euston work and other West Coast rail upgrades as much as possible to minimise disruption to passengers.

Passengers can find out more information at www.nationalrail.co.uk/westcoast

Notes to Editors

*For Euston to be the London terminus for HS2 - two of the approach lines to the station, will be closed for a combined total of 12 weeks. This will be split into two separate six-week closures:

  • 02 April to 17 May 2021
  • 17 July to 31 August 2021

Preparatory work on the approach lines at Euston to enable HS2 will be carried out over a number of weekends, resulting in platform and services alterations, including some being reduced between April and August next year.

The rail industry has worked closely to combine the Euston work and other West Coast rail upgrades as much as possible to minimise disruption to passengers. 

Most services into and out of Euston will run during the work on the approach lines to prepare the way for high speed rails, with platform and some service alterations 

West Coast train operators and Network Rail are also working together to develop a dedicated timetable to support customers during this period, which will also reflect potential and ongoing changes to travel demand due to Covid-19.

As well as being one of the biggest investments in Euston for decades, this is also one of the most complex infrastructure changes ever to take place at the station.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk