Oxford station upgrade moves forward with plans for new platform and western entrance:  Dan Ogden

Thursday 26 Nov 2026

Oxford station upgrade moves forward with plans for new platform and western entrance

Region & Route:
Wales & Western: Great Western

Plans for the next major phase of Oxford station’s transformation are moving forward, with a new platform and western entrance planned to create more space for train services and make the station easier for passengers to use. 

Network Rail is progressing plans for a new through platform and an additional entrance on the western side of the station, with both currently targeted to open by summer 2029, subject to funding being released and the main construction contract being awarded. 

The improvements are designed to help Oxford station meet growing demand in the years ahead, including supporting potential future services linked to East West Rail, the reopening of the Cowley Branch Line and other developments in and around the city. 

Design work on the new western entrance has restarted and is being updated to reflect the latest forecasts for passenger numbers, including travel associated with East West Rail and the Universal Resort in Bedfordshire. The design is expected to progress through the planning process by mid-2027. 

Current proposals for the western entrance include ticket machines, ticket gates and toilets, with cycle parking and areas for passenger pick-up and drop-off also being considered. 

Tom Pierpoint, industry programme director for Network Rail’s Great Western route, said: 

“The new platform and western entrance are a really important part of preparing Oxford station for the future, giving passengers another way in and out of the station while creating the extra capacity needed to support more train services. 

“We know delivering the next phase of the upgrade will have an impact locally, particularly around Roger Dudman Way. We’re looking carefully at how we can reduce that disruption and will keep residents and businesses informed as the plans develop.” 

Under the indicative programme, Roger Dudman Way would need to close to through traffic for around 20 months to allow major construction work to take place. 

Pedestrian and cycle access would be maintained, while a diversion route would also be put in place for vehicles requiring local access. 

The closure would allow teams to build new road and rail bridges at Sheepwash and safely divert utility pipes and cables. The plans include a road diversion to the north and a temporary footbridge to maintain access to and from Roger Dudman Way. 

Network Rail is working with its contractors and partners to identify ways of reducing the length and impact of the closure, including carrying out some activities around the clock where appropriate. Further information for residents, including details of piling and other construction activity, will be shared once the programme has been finalised.

Botley Road and its pedestrian walkways are expected to remain open throughout the remaining work. 

Ahead of this next stage of station improvements starting, work on the previous stage is being completed, including completing the temporary junction from Cripley Road to Roger Dudman Way, replacing temporary railings with permanent, and repairing paving in Frideswide Square. Work on the new southern walkway along Botley Road is taking place overnight to minimise disruption. 

The new western entrance and platform form part of a wider ambition to improve Oxford station and the surrounding area. 

Separate longer-term proposals include a potential new eastern entrance, a cycle hub, better connections with other forms of transport, improvements to public spaces and development around Beckett Street. 

Public consultation on these wider proposals is provisionally planned for late May to early July 2027. 

Network Rail also plans to hold regular stakeholder update sessions during 2027, alongside updates through newsletters, its website, Facebook and direct letters to people affected by the work. 

Residents and businesses can contact the project team at OxfordFeedback@networkrail.co.uk. 

ENDS 

 

Notes to Editors

 

  • Construction programme: Preparatory work is planned for early 2027, followed by construction of the bridges and new platform. Work on the western entrance is currently scheduled across 2028 and 2029. 

 

  • Future train services: The additional platform would provide capacity to support potential future services, including East West Rail and possible services between Cowley and London Marylebone. No new train timetable is being announced as part of this update. 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - James Crook
Senior Media Relations Manager
Network Rail
07732 644202
james.crook@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk