Friday 27 Nov 2026
Just over one week to go until £115m Manchester Airport railway station improvements begin
- Region & Route:
- North West & Central
- | North West & Central: North West
Passengers travelling to or from Manchester Airport are being advised to plan ahead and check their journeys as Manchester Airport railway station prepares to close for one day on Sunday 6 December.
The temporary closure, now just over a week away, will allow Network Rail and its contractor Kier to begin a major £115 million programme of improvements at Manchester Airport station.
Manchester Airport railway station will be closed throughout Sunday 6 December 2026, reopening as normal on Monday 7 December.
Passengers planning to travel to or from the airport via train are being asked to:
- Check their journey before travelling
- Allow extra time
- Follow advice from their train operator
- Speak to staff if they need assistance with their journey
Rail replacement buses will operate between Manchester Victoria, Manchester Piccadilly and Manchester Airport.
During the closure, engineers will install a new utility bridge across the railway to carry electrical cables. This is an important stage which will allow an existing bridge structure used by Manchester Airport Group to be removed at Easter 2027, before a new structure is constructed later in the year.
Network Rail is working closely with Manchester Airport Group, Transport for Greater Manchester and train operators to minimise disruption and keep customers moving.
Simon Daly, Network Rail senior sponsor, said: “With just over a week to go, we’re reminding passengers that Manchester Airport station will be closed on Sunday 6 December and asking everyone to check their journey before travelling.
“This work is an important first step in our £115 million investment and will help create more capacity, allow longer trains to serve the station and improve the reliability of journeys for years to come.”
“We know that there’s never a good time to close the railway, but we’ve worked closely with our partners to ensure customers are kept on the move. I'd like to thank everyone for their patience and understanding while this work takes place.”
Network Rail will deliver the major programme of improvements between now and 2028.
The £115 million investment will see:
- Platforms 1, 2 and 3 extended
- Track layouts on the approach to the station upgraded
- Train signalling systems modernised
Once complete, the improvements will create additional capacity, support the operation of more trains and help provide more reliable and efficient journeys.
Chris Nutton, Major Projects & TRU Director at TransPennine Express, said: “We’d like to thank our customers in advance for their patience while this major investment is delivered at Manchester Airport station. The £115 million upgrade will bring long-term benefits for everyone who travels through the station, creating more capacity, improving reliability and supporting more frequent services in the future.
“We are working closely with Network Rail and our industry partners to minimise disruption during the work and would encourage customers to check their journey before travelling while these essential upgrades are taking place.”
For the latest information, please visit www.nationalrailenquiries.co.uk.
The programme will also support future passenger growth and improve connections to Manchester Airport, strengthening its role as a gateway for business, tourism and international travel.
The project forms part of the wider Manchester Rail Upgrade, which is creating a bigger, more reliable and better-connected railway for passengers across the North West.
Passengers can find further information about the work at www.networkrail.co.uk/manchester-airport-station.
Notes to Editors
Manchester Rail Upgrade
This work forms part of the Manchester Rail Upgrade (formerly called the Manchester North West Transformation Project - MNTP) which is a major investment programme to boost future rail capacity across the North West, delivering more trains, more seats and improve journey reliability.
Major projects already delivered are:
Schemes ongoing:
- New turnback sidings at Oldfield Road and Brewery Junction and overhead electric line installation in Manchester
- New signalling for the new sidings and platforms at Salford Crescent, Brewery Junction and Oldfield Road.
- Manchester Airport station remodelling: Platform extensions to allow 2x6 car trains to use the platforms at the same time and a remodelled railway junction on the approach
Projects in development:
- Revisions to the railway layout at Manchester Oxford Road alongside passenger accessibility upgrades
- Work to increase train capacity and operational flexibility at Manchester Piccadilly
Manchester Airport station work
- The closure is the first in a planned package of engineering work taking place between the end of 2026 and the middle of 2028.
- Network Rail is investing £115 million to upgrade Manchester Airport station.
- A 29-hour closure affecting rail services to and from Manchester Airport station is planned on Sunday 6 December 2026 for one day only.
- Rail replacement buses will operate between Wilmslow and Manchester Airport.
- Customer-handling teams will be in place to support passengers.
- Platforms 1, 2 and 3 will be extended to create capacity for more trains while the junction outside the station will be reconfigured to improve train movements and operational flexibility.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Henry Hughes
Senior Communications Manager - North West Route
Network Rail
0330 8540100 (Option 3)
henry.hughes@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk