October half-term railway upgrades completed between Staines and Windsor: 30 Wooden wheeltimbers

Monday 2 Nov 2026

October half-term railway upgrades completed between Staines and Windsor

Region & Route:
Southern
| Southern: Wessex
  • Bridge and track upgrades formed part of a wider plan to reduce delays and improve reliability between London Waterloo, Staines and Windsor & Eton Riverside
  • Engineers worked around the clock for seven days whilst the line was closed
  • Engineering work took place between Monday 26 October and Sunday 1 November affecting train services in the Staines, Windsor, Hounslow, Feltham and Virginia Water areas

Improvements were completed on South Western Railway’s (SWR) route and Network Rail Wessex route between Staines and Windsor this October.

During the October half-term, from Monday 26 October to Sunday 1 November, engineers carried out essential track and bridge maintenance work between Staines and Windsor & Eton Riverside, as part of ongoing investment in railway infrastructure to improve reliability and resilience for customers across the network.

Buses replaced trains between Monday 26 October and Sunday 1 November.

At a bridge between Staines and Wraysbury, engineers replaced 28 wheel timbers, the wooden blocks that support passing trains, to ensure trains can continue to travel safely at full speed, helping keep services running on time.

In Windsor, engineers replaced 30 long timbers, wooden blocks that support multiple tracks, on the approach to Windsor & Eton Riverside station. The new timbers were installed to support the more than 70 train services that use the station every weekday and improve the railway’s long-term resilience.

Engineers also renewed the switches and crossings near Staines station, where there is an important entry point for trains to enter service.

The work follows SWR and Network Rail Wessex’s plan to improve reliability across the network, including a £15 million investment in track and signalling improvements for the busy critical corridor between London Waterloo and Woking, targeting some of the most common causes of delays.  

Services between London Waterloo and Windsor & Eton Riverside join this corridor at Queenstown Road (Battersea), where further improvements are being delivered to support more reliable journeys.

Thomas Desmond, Operations Director for South Western Railway and Network Rail Wessex, said:

“These upgrades represent an important investment into the railway's future, improving reliability, reducing the likelihood of disruption and ensuring that we continue to provide a safe and dependable service for our customers.

“We’re thankful to our customers for their patience while we carried out these essential works over the October half- term.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Luis Moya
luis.moya@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk