Monday 16 Mar 2026
North Devon railway passengers asked to plan ahead during March engineering work
- Region & Route:
- Wales & Western: Western
Network Rail will carry out essential track renewals, structural surveys and other work on railway lines in North Devon later this month. For a week between Saturday 21 and Sunday 29 March, train services will be affected between Exeter and Barnstaple, and on the Okehampton route, while vital maintenance is completed.
The work is needed to ensure the continued safe and reliable running of the railway. It will also enable an increase in the speed trains can travel along the track in the future, helping to reduce journey times.
During the eight-days, working on two track renewals between Exeter and Barnstaple (at Chenson and between Barnstaple and Taw), engineers will install:
· 2.7 kilometres of track
· 3,000 tonnes of ballast (track stone)
· 4,236 sleepers
The job will be supported by up to 80 workers out on track at the two locations, with engineering trains and Road Rail Vehicles (specialist diggers) and a tamping train to compact the new stone.
Making the most of the opportunity, while trains aren’t running, engineers will also be carrying out:
· minor track adjustments
· drainage checks and clearance
· inspections on bridges, viaducts, retaining walls and signals
· minor lineside vegetation management
Travel information
Buses will replace all trains that would normally operate via Crediton from Saturday 21 to Sunday 29 March.
As an alternative, valid rail tickets can also be used to travel on the number 5, 5A, 5B and 5C Stagecoach services or the number 66 Dartline service.
Other train services will still be operating on the main line at Exeter St Davids, including a reduced service between Exeter St Davids and Exeter Central.
However, on Sunday 29 March, track maintenance work will also mean buses replace trains between Exeter St Davids and Tiverton Parkway before midday.
Network Rail lead portfolio manager Mark Parker said:
“We appreciate this work represents further disruption to train services in this area, following on from last month’s closures due to flooding. I’d like to thank passengers and residents in advance for their understanding.
“This track renewal work has been planned for some time as an important part of our maintenance regime. It’s vital that we do take time to replace worn components and make improvements to ensure continued safe and reliable journeys for passengers.
“To minimise the overall impact of our work, we are incorporating as much work as possible within this period, with other teams completing additional maintenance and inspections while the railway is closed.”
GWR’s Station Manager for Mid-Devon, Melanie Harvey, said:
“We apologise for the inconvenience this may cause but the work planned will help us to maintain our train services in the area for years to come.
“Rail replacement services are planned for those stations affected and ticket acceptance is also in place on local bus services in the area as an alternative.
“It’s important that customers are aware these alternative travel arrangements could make journey times much longer, so please plan ahead."
Please allow extra time for your journey and check before you travel at nationalrail.co.uk or GWR.com/upgrade
Please note: The lifts at Exeter St Davids station will be out of use until April. Customers with reduced mobility are asked to consider travelling from an alternative station if possible. There is an alternative step free route that can be used, but only with staff assistance. Please speak with staff if you need help or alternatively contact Great Western Railway here.
ENDS
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - James Crook
Senior Media Relations Manager
Network Rail
07732 644202
james.crook@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk