Nitshill Road, south of Glasgow, will close overnight on eight consecutive Saturdays while Network Rail engineers carry out work to repair and strengthen the railway bridge over the A726.

The refurbishment of the bridge, at Nitshill station, is part of a wider, rolling programme of maintenance work on structures which is designed to extend their lifespan and keep the network safe and reliable. It represents an investment of circa £1m to protect and prolong the life of the bridge.

Work on the bridge, includes improving the drainage and clearing adjacent vegetation, strengthening girders, repairing masonry, blast cleaning and repairing the metalwork, applying corrosion protection and painting.

To deliver this work safely and efficiently, the road needs to close overnight each Saturday night from February 22, to enable engineers to erect scaffolding.  Pedestrian and cycle access will be maintained throughout the project.

In addition to the Saturday night road closures, traffic management will be in place from February 22 until April 13 which will reduce the road to single lane controlled by temporary traffic lights.

Allison Flanagan, Network Rail project manager, said: “We know that Nitshill Road is a busy and important route for local traffic and we do not take the decision to request its closure lightly.

“We understand the impact that this potentially will have for both road users and those communities adjacent to the bridge works. However, this is the most efficient and safest way to undertake the work required on the bridge.

“We will deliver the work in just 12 weeks which is a logistical challenge but we have planned the job carefully with our contractors and will complete it with the minimum possible inconvenience to the local community.”

Network Rail has worked with Glasgow City Council to put in place an appropriate ‘all vehicle’ diversion and all local access has been retained either side of the bridge to industrial units and the near-by shops and supermarkets.

If you have any questions about this work you can contact Network Rail’s 24 hour national helpline on 03457 11 41 41.  For latest information and progress updates follow on twitter @NetworkRailScot

Notes to Editors

Work will begin at Nitshill Road on Monday, February 10 and will be ongoing both day and night-time until Friday, May 1.

Day shift is Mon – Fri 7am – 5pm

Night shift working is Saturday 10pm – 8am & Sun – Thurs 10pm – 7am

A single lane closure controlled by traffic lights will be in place from February 22 until April 11

Full road closures will be in place overnight Saturday into Sunday from February 22 until April 13 (inclusive)

An ‘All vehicle’ diversion route will be in place each Saturday night while the road is closed. It runs via Glasgow Road & Parkhouse Road.

An ‘All vehicle’ diversion route is required to accommodate the largest vehicles which normally use the closed road. However, other streets may be appropriate for smaller vehicles.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk