Demolition work complete on Glasgow Queen Street station: 4 Oct 18 Timelapse camera image

Friday 5 Oct 2018

Demolition work complete on Glasgow Queen Street station

Region & Route:
Scotland’s Railway: Scotland

The redevelopment of Glasgow Queen Street station reached another major milestone this week as the project team completed all of the demolition work needed to start building a bigger and brighter transport hub.

To mark the moment, Network Rail has released new time-lapse footage showing the changing landscape of the station. The footage features the removal of the eight-storey Consort House building, Consort House annex and the Millennium Hotel’s 1970’s extension from the city’s skyline.

Since January, the demolition team has worked more than 26,000 hours to safely remove over 14,000 tonnes of redundant material from the station site – the equivalent of 700 skips.

With 94% of demolition material now recycled and avoiding landfill, it is being given a new lease of life, becoming new products such as aggregate for the construction trade or wood chippings for equestrian centres. 

Network Rail programme manager Tommy McPake said: “Demolishing redundant buildings in the heart of Glasgow and in a live station environment has been extremely challenging, with over 47,000 customers passing through the station each week day.

 “By completing this stage in the project, we now have the additional space required to progress with transforming Glasgow Queen Street station. We are proud that our planned demolition method has ensured nearly all of the material removed from the site has been recycled for future use. 

“I’d like to thank customers and the surrounding community for their patience as we build a bigger and brighter station for the city.”

The project team is now undertaking piling work to support the future expanded station concourse and work is progressing to build the new station basement.

Once completed, in 2020, the redeveloped Glasgow Queen Street station will provide extended platforms for longer trains of up to eight carriages - meaning more seats for passengers – and an expanded concourse with more circulation space in a contemporary and distinctive building. 

The new station is being delivered as part of the Scottish Government-funded Edinburgh-Glasgow Improvement Programme.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk