New £10m depot unveiled to maintain Manchester's railway for passengers: Guide bridge wide external

Monday 16 Mar 2026

New £10m depot unveiled to maintain Manchester's railway for passengers

Region & Route:
North West & Central
| North West & Central: North West

A £10m new rail maintenance depot has been unveiled to keep passenger and freight trains moving smoothly through Greater Manchester.

The high-tech facility at Guide Bridge is the new home for over 120 Network Rail staff who work night and day to make the railway safe and reliable.

In just over a year, the two-storey building has been built on a 2.3-acre former railway siding.

It brings four separate track maintenance teams under one roof for the first time, having previously been based in separate temporary cabins with outdated facilities on the same site.

It's hoped that bringing the staff together will mean better collaboration and faster response times to fix railway faults – leading to fewer delays for passengers.

The building came in £6m under budget thanks to a range of efficiency measures including innovative construction sequencing, material specifications and challenging standard railway approaches.

Clare Waller, Network Rail’s interim North West route director, said: “It’s fantastic to see this new depot at Guide Bridge now in use and provide modern facilities for the teams based there so they can respond to incidents and maintain the railway for passengers and freight in Greater Manchester.

“The teams have worked across multiple temporary buildings and not the best of environments for many years, so I’m sure this new striking building with top-notch accommodation will make a massive difference to them and the work they are able to achieve.”

Everything has been built to modern accessibility standards, with a lift between floors, accessible toilet and changing rooms.

The male locker room has 120 lockers and female equivalent 20 lockers, both with showering and toilet facilities, while the mess room has capacity for 100 staff at any one time.

There is an array of 60 solar panels on the depot’s roof which will provide approximately 44% of the depot’s energy, with a buy-back scheme set to be introduced so it can generate revenue with any surplus being supplied back to National Grid.

Ten new electric vehicle charging points have also been installed the depot as part of Network Rail’s commitment to move to all-electric vehicles in future.

Network Rail’s Maintenance Delivery Units (MDUs) are operational day and night with shifts around the clock for teams to be able to respond to incidents and carry out overnight engineering work.

For more information about how Network Rail looks after the railway visit: https://www.networkrail.co.uk/our-work/looking-after-the-railway/

Notes to Editors

The project took 62 weeks to complete and was managed by Network Rail Capital Delivery Buildings and Civils team and delivered by principal contractor Galliford Try.

The multi-disciplinary teams now based in the one building include: Permanent Way, Off Track, Lubrication, and Welding & Grinding.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk