Network Rail to refine resilience plans for vital stretch of Devon railway: CrossCountry HST passing Holcombe beach

Wednesday 14 Oct 2020

Network Rail to refine resilience plans for vital stretch of Devon railway

Region & Route:
Wales & Western: Western

Plans to improve resilience along a vital 1.8km stretch of railway in the south west will be refined by Network Rail following substantial feedback from the community, passengers and businesses.

More than 1,600 people responded to a six-week public consultation on proposals for the line between Parson’s Tunnel and Teignmouth in Devon, which is bordered by steep cliffs on one side and the sea on the other.

The plans would see the track realigned to create space to stabilise the hazardous cliffs and protect the railway for future generations. A realigned coastal footpath would also be built, along with a new landward path and accessible footbridge across the railway.

Earlier this year, a second round of consultation on the proposals saw more than 2,840 people attend 11 community events at which a 10m-long scale model of the scheme was on display. Since the first round of consultation in 2019, the plans had been revised to retain more of the beach and improve leisure access.

Key findings from the 2020 consultation include:

  • 73 per cent of people agreed/strongly agreed that this stretch of railway needs to be more resilient, with 13 per cent disagreeing/strongly disagreeing and 14 per cent undecided.
  • 41 per cent of people agree/strongly agree with Network’s Rails proposals for improved resilience, with 51 per cent disagreeing/strongly disagreeing and eight per cent undecided.
  • More than half (54 per cent) of people supported or strongly supported the creation of a new coastal path and amenity
  • The 2020 consultation saw an increase of more than 1,200 attendees and 1,100 responses from the 2019 events

Network Rail now plans to refine the proposals after analysing the 1,605 responses from the second round. The consultation asked people to provide further comments on the plans and/or give feedback on how they could be improved.

More than 2,100 comments were received on issues ranging from the construction timeline and impact on the environment to loss of heritage features and effect on the local economy.

Mike Gallop, Network Rail’s director for the Western route, said: “We would like to thank everyone who responded – we have read and reviewed every single comment. We received some good and considered feedback which can positively influence our plans, and it is important that we get this significant scheme right.

“As a result of the feedback we are now refining the plans even further with a view to then sharing these revisions with the public next year. We’ll now spend the next few months working through this detail, once we have our refined plans we will schedule a further round of public consultation in 2021.

“This means that we won’t be applying for a Transport and Works Act order to seek consent for the scheme this year as we had previously indicated in early communications. We will only proceed to this stage when we’ve done this further work and engagement.”

A summary of the consultation outcomes, along with the comments submitted, can be viewed online at networkrail.co.uk/Teignmouth.

Network Rail will also be writing to 16,000 households within the consultation boundary, with a summary of the findings

Notes to Editors

Notes to editors: The interim consultation report is available at networkrail.co.uk/teignmouth

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk