Tuesday 24 Nov 2009
NETWORK RAIL TO BUILD NEW TEMPORARY STATION TO HELP WORKINGTON FLOOD VICTIMS
- Region & Route:
- National
Cumbria rail structures safe
Expertise and assistance offered to County Council
Network Rail starts work tonight to build a temporary railway station on the north side of the River Derwent at Workington to ease the access problems the people of the town are experiencing following the floods.
In the last 24hrs the company has identified a site for a new temporary station that could help alleviate some of the problems being experienced by the residents of Workington and the surrounding villages. The new station will be built on waste-land just over ½ mile to the north of the existing station, reconnecting the two halves of the town that have been cut off following flood damage to the footbridges and road bridges in the area.
Robin Gisby, director operations and customer services said: “We have a wealth of experience and engineering expertise that we felt should be put at the disposal of the Cumbrian authorities. Our people will work round the clock to build a temporary rail station, north of the river, to help re-connect the town and ease people’s travel problems.”
Network Rail has agreed a two-year lease of land owned by Allerdale Borough Council off the A596 immediately north of St Helens Business Park, opposite the Plaza Cinema. The two-platform station, linked by a footbridge, will have lighting, a waiting room and a gravel car park, and will be built and ready for its first passengers by the weekend.
Jo Kaye, route director, said: “Through aerial surveys we identified several potential sites for a temporary station. The council, despite being under considerable pressure, worked with us to quickly identify the best solution and a site was chosen. Work will start tonight and we will have the station open just as soon as we can."
Network Rail has also had its own structures engineers examining rail bridges throughout the county and all have been passed as safe enabling a normal train service to run.
As one of the UK’s biggest engineering companies with extensive experience in finding and delivering engineering solutions in very short time-frames, the company has offered Cumbria County Council its expertise and resources in structures management to help with the onerous task the council faces examining its 1,800 bridges. The council was also offered future resources to help the re-building efforts.
Transport Minister Sadiq Khan said: "I would like to commend Network Rail for the quick work they are doing here and I’m sure it will help the people of Workington."
Notes to editors
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk