NETWORK RAIL SETS OUT TIMETABLE FOR THAMESLINK COMPLETION: Blackfriars station at night

Monday 12 Dec 2011

NETWORK RAIL SETS OUT TIMETABLE FOR THAMESLINK COMPLETION

Region & Route:
National

The transformation of rail travel in London came a step closer this morning when the first longer, 12-carriage train began its journey from Bedford to Brighton just before 7am.

By 9:25am, when it arrived at its destination at Brighton, it had passed the longer platforms, new signals and upgraded power facilities, all provided by Network Rail as part of the Thameslink programme to allow longer, more frequent trains to use the route.

To make this possible, Network Rail has lengthened platforms at 14 stations across the route. That’s an additional 4km of extra platform and carriage space, twice the length of Luton Airport runway, or 34 football pitches laid end-to-end. More than 160km of new power cable has been laid to provide the power demanded by longer trains, and signalling systems along the route and through central London have been upgraded and replaced. The vast majority of this work has been completed overnight and at weekends to reduce disruption to passengers.

The improvements were not limited to the longer, less crowded trains. At Farringdon station a new spacious ticket hall came into use this morning. At 1,600 square metres – the equivalent of six double tennis courts – this spacious hall will provide the additional capacity that will be required, not only for the longer, more frequent services made possible by the Thameslink programme but also future Crossrail services. Farringdon is now set to be transformed into London’s newest transport hub. From 2018 Thameslink, Crossrail and London Underground services will meet to provide over 140 trains an hour.

At Blackfriars, passengers also saw improvements, with a new station entrance to the north. This follows from the new southern entrance that opened last Monday, allowing passengers direct access to the South Bank and Bankside for the first time in 125 years.

Jim Crawford, Network Rail major programme director for the Thameslink Programme, said: “The pace of improvement for passengers as a result of the Thameslink Programme is really picking up now. For four years we have been working intensively behind the scenes to get this work done and its great to see the plans coming together to deliver real benefits.”

This is set to continue, with refurbished underground stations reopening at both Blackfriars and Farringdon in February and the completion of the major National Rail stations on both sites in time for the Olympics next year.

First Capital Connect operates the train service on the Thameslink route. Managing director Neal Lawson said: "Passengers with First Capital Connect need more space on trains to and from the capital and we're working hard to ensure the Thameslink Programme achieves just that. Since 2006 we've added almost a third more rush hour seats to the route; today we've added 3,200 more. This, together with the new station facilities coming on line at Blackfriars, Farringdon and West Hampstead, will help improve our service still further.”

The Thameslink Programme will see longer trains and more frequent services on the route from Bedford to Brighton through central London. Alongside extensive resignalling, power upgrades and platform extensions along the route, the rebuild of Blackfriars station, improvements at Farringdon and the planned reconstruction of London Bridge, will combine in 2018 to provide a metro-style service through central London, with trains running every 2 ½ minutes.

Thameslink’s countdown to completion

September 2011
- Completion of first phase of major resignalling work across the route.

October 2011
- Work begins to install 4,400 solar panels on the roof of Blackfriars, creating London’s largest solar array

November 2011
- Completion of the award of the three London Bridge Area Partnership contracts for the track, signalling and station redevelopment at London Bridge.
- The final platform extension is completed, allowing longer trains to call at stations along the route.

December 2011
- First passengers use new Blackfriars entrance on the south bank of the Thames
- First 12-carriage Thameslink trains serve the route
- New northern entrance opens at Blackfriars
- New ticket hall comes into use at Farringdon
- New station for West Hampstead Thameslink opens

February 2012
- New London Underground stations open at Blackfriars and Farringdon

Summer 2012
- Completion of Key Output One, with major station upgrades and , capability for 12-carriage trains fully operational ahead of Olympic and Paralympic Games

2013
- Commencement of Key Output Two works, focussed on redeveloping the station and railway at London Bridge.

2018
- Completion of the Thameslink programme, allowing a more frequent (metro style) rail service to and through the capital.

Notes to editors

About the Thameslink Programme
The Thameslink Programme is a £6bn Government-funded scheme to transform one of the UK's busiest rail routes. The programme will dramatically increase capacity and improve accessibility to and through the heart of London. It will deliver major long term benefits for passengers, the environment and the UK economy including new stations, new destination choices and new, longer, more frequent trains.

In this first phase of the Thameslink Programme, Network Rail has extended platforms at 12 stations north of London on the Thameslink route. Power supplies have been upgraded and two central London stations – Blackfriars and Farringdon – are being redeveloped.

The second phase of the Thameslink Programme will be completed in 2018 at which point London Bridge station will have been rebuilt connecting to new destinations on the Thameslink route.

About the longer 12-carriage trains
Today’s new December timetable sees the first 12-carriage service operating on First Capital Connect’s Bedford-Brighton Thameslink route.

The new 12-carriage service of four trains in the morning and four in the evening adds almost 2,000 extra seats at the busiest times of the day to the Thameslink route.

Furthermore, using existing rolling stock, First Capital Connect has lengthened four 4-carriage services to 8-carriages, providing over 1,200 extra seats in the morning and evening rush hours combined.

About Farringdon’s National Rail ticket hall
At 1600 square metres, the new National Rail ticket hall has been built by Network Rail to accommodate passengers for First Capital Connect’s first longer, 12-carriage trains on the Bedford-Brighton Thameslink route.

The new ticket hall also provides the additional capacity that will be required with future Crossrail services from 2018. Lifts in the new ticket hall will open in 2012.

The London Underground entrance is currently closed for refurbishment, passengers are being redirected to use the new Turnmill Street concourse. The entrance will reopen on Monday 6 February.

About the Redevelopment of Blackfriars station
Blackfriars station will be the first rail station to span the Thames, offering direct access to both the north and south banks of the river.

When complete, it will be the largest solar bridge in the world, with over 4400 solar panels providing 50%of the stations energy.

The project sees the widening of the existing Victorian rail bridge, as well as the redevelopment of the London Underground station.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk