Network Rail reaches major milestone in railway upgrade in Northamptonshire: Network Rail reaches major milestone in railway upgrade in Northamptonshire

Wednesday 20 Jun 2018

Network Rail reaches major milestone in railway upgrade in Northamptonshire

Region & Route:
| Eastern

Network Rail has successfully completed 12 weeks of major improvement work to the railway in Northamptonshire as part of the Midland Main Line Upgrade.

The work saw two of four rail lines closed to allow Network Rail engineers to carry out major work to track, drainage, bridges and viaducts in the county.

During the work, 57 engineering trains were used to install four kilometres of new track, over half a kilometre of track was renewed and over 300 tonnes of ballast, the stones which support the track, was laid.

Irchester and Wellingborough viaducts and Sharnbrook Tunnel were strengthened and repaired and Halsey Road bridge in Bedford was demolished and reconstructed to support increased rail traffic which will use the additional and existing lines in the future.

Whilst a major milestone has been reached, work continues on the Midland Main Line Upgrade in Northamptonshire as Bush bridge, Finedon Road bridge and Station Road bridge in Wellingborough continue to be reconstructed.

Network Rail and East Midlands Trains worked together to keep passengers moving throughout the work.

Ed Akers, Principal Programme Sponsor at Network Rail, said: “We’d like to thank passengers for their patience whilst this vital upgrade was carried out and apologise for any disruption this caused. We’ve worked closely with East Midlands Trains to keep this to a minimum.

“Whilst this major milestone has been reached, we are still continuing with work in the county as part of the Midland Main Line Upgrade. This work will see three bridges reconstructed to allow electrified wires to be positioned safely beneath them and we look forward to passengers seeing the benefit once this work is completed.”

 ENDS

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Amy Brenndorfer
Programme Manager, Communications
07730359569
Amy.Brenndorfer@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk