Network Rail on track to reopen East Grinstead line for Monday – but please do check before you travel and only travel if you have to: East Grinstead landslip

Friday 27 Mar 2020

Network Rail on track to reopen East Grinstead line for Monday – but please do check before you travel and only travel if you have to

Region & Route:
Southern

Network Rail remains on track to complete landslip repairs to reopen the East Grinstead railway line for key workers and passengers for whom travel is absolutely essential, on Monday 30 March, although the impact of the Coronavirus outbreak could still cause a delay.

With Thameslink and Southern also running a further-reduced timetable from this date - new timetable - passengers are encouraged to check at national rail enquiries before they travel.

The railway has been closed between Lingfield and East Grinstead since 12 February when a railway embankment near Cookspond Viaduct, in Dormansland, began to slide. Since then, no fewer than five further sites have suffered landslips on the route and Network Rail has been working with BAM Nuttall to repair the line.

The repairs are almost complete and testing will continue over the weekend.

Network Rail Southern Region’s managing director, John Halsall, said: “We are on course to return this railway to use on Monday, at an absolutely crucial time, with key workers relying on us to get to their jobs.

“However, I can’t be as confident as I would like to be simply because we are seeing increasing numbers of our colleagues having to leave work to self-isolate and we don’t know what those numbers will be and who will be affected over the next two days.

“So my message to passengers is firstly, please only travel if you absolutely have to, and then secondly please check before you travel on Monday. It’s been an incredible effort by everyone who has worked on the project to get so far so fast and I am so proud of their work, but we have to be realistic and admit the challenge we face.

“Thank you to everyone for your patience.”

Steve White, Chief Operating Officer at GTR, which runs Thameslink and Southern services, said: “Our important message to everyone during this national emergency remains not to travel unless absolutely essential but for those key workers and people who have no choice, the completion of this work will be good news reducing your travel time.

“We would like to thank customers for their patience during this essential work. Network Rail really has pulled out all the stops to repair the landslips in this area and I applaud them for their efforts on behalf of the community and the railway."

Notes to Editors

Three of the landslips took place on the same stretch of embankment, constructed in the Victorian period of Wealden Clay and repaired with steam engine ash (not to anywhere near modern standards or materials).

The very wet winter put the poorly-built embankment under strain and it gave way. We have repaired the line by building a wall of sheet piles sunk 13m into the ground, backfilled with railway ballast.

Two other landslips took place in a cutting, where the sides were built too steep to withstand the wet weather. In those locations the slope has been regraded – made less steep.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Chris Denham
Senior media relations manager
020 3357 7969
07515 626530
chris.denham@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk