Network Rail on-track to deliver £8m of upgrades this Christmas: Christmas workers 2 16x9

Friday 20 Dec 2019

Network Rail on-track to deliver £8m of upgrades this Christmas

Region & Route:
Scotland’s Railway: Scotland

Network Rail engineers will deliver £8m of enhancements on Scotland’s Railway over the Christmas and New Year holidays.

More than 2,500 railway staff will be out at sites across the country to complete vital projects – renewing life-expired tracks and junctions, upgrading signalling systems and enhancing our major stations.

In Edinburgh, From Christmas Day to December 29, Haymarket East junction will undergo a major upgrade – including renewing four sets of points (rails which move to transfer trains from one line to another) and replacing 250m of track.

One of the busiest junctions on Scotland’s Railway, Haymarket East is used by up to 30 trains an hour. This upgrade will help to improve the reliability of the track and will mean the junction won’t need to be renewed again for decades.

On Friday, December 27, and Saturday, December 28, trains will be unable to pass through Haymarket and a replacement bus service will be in operation into Edinburgh Waverley from stations to the west of the city.

In Glasgow, on Christmas Day and Boxing Day, new track will be laid on the approach to Glasgow Central station with engineers working to renew 300m of line at Shields Road on the south of the Clyde.

In Lanarkshire, a major signalling upgrade will be completed with the control of signalling on the West Coast Mainline transferred from Motherwell Signalling Centre to the new, £200m West of Scotland Signalling Centre in Glasgow.

Kris Kinnear, Network Rail Scotland’s capital delivery director, said: “These projects are vital to the long-term future of Scotland’s Railway and part of the £4bn investment being made in our network over the next five years.

“Renewing this ageing infrastructure will improve the reliability of the service we provide and will also help to reduce long-term maintenance costs.

“Renewing complex infrastructure cannot be accomplished without short-term closure of the railway and we work over Bank Holidays to try to limit disruption for our customers as fewer people travel at this time. Our engineers have carefully planned these projects to be completed as quickly as possible.”

Across Britain, Network Rail will be investing £111m over the festive period to improve and upgrade the rail network with 20,000 members of staff working at more than 300 sites.

A breakdown of how journeys will be affected over the Christmas period can be found by visiting www.nationalrail.co.uk or https://www.scotrail.co.uk/christmas.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk