Major repair and refurbishment work has been completed at Hurst Green station to upgrade and improve the platforms for passengers.

Hurst Green railway station is on the Oxted line in southern England and serves Hurst Green in Surrey. The trestle sections of the platforms at Hurst Green station were upgraded along with trestle leg repairs and slab replacements; these vital works were planned to be delivered in a 52 hour possession which was later reduced to 27 hours.

The project team were able to plan an approach which involved delivering part of the works during the week while working at night in a safe manner.

The project also received positive feedback from station users whilst demobilisation was taking place, highlighting the success of the project’s strategy in integrating the Putting Passengers First strategy at the core of the delivery plan.

Shaun King, Sussex route director for Network Rail, said:

“This upgrade has made a big difference to Hurst Green station by improving the experience for passengers. These improvements are a vital aspect of our strategy to provide a safe, reliable and efficient railway and this project will make sure that the platforms will be a reliable asset for years to come.”

Chris Fowler, Customer Services Director for Southern and Gatwick Express, said:

“We thank Network Rail for these vital repairs to the platform structures at Hurst Green. Together with the programme of improvements we are undertaking, including the recently-completed waiting area and automatic doors at the main entrance, we are delighted to offer our customers a better all-round experience at their station.”

The typical off-peak service in trains per hour is:

  • 2 tph to London Victoria (calls at all stations between Oxted and East Croydon)
  • 1 tph to London Bridge (runs non-stop between Oxted and East Croydon)
  • 2 tph to East Grinstead
  • 1 tph to Uckfield via Crowborough

Hurst Green has a rich history and the first regular London-Hastings passenger carrying coach ran in 1745 taking three days to cover the route in either direction - reduced to one day by the end of the century.

The original Hurst Green Halt opened 1 June 1907 with short wooden platforms, sited between the road bridge and the junction of the East Grinstead/Uckfield lines. This halt was closed on 12 June 1961 and the present station was opened on the northside of the bridge.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Leonard Bennett
Leonard.Bennett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk