Network Rail engineers work non-stop to reopen Yorkshire rail line closed by landslip

Region & Route:
| Eastern

Network Rail has successfully reopened the rail line between Leeds and Ilkley after a landslip caused it to close last week.

The incident occurred on Tuesday, 3 April when a Northern driver reported seeing a tree perched precariously over the southern portal to Springs Tunnel, to the south of Guiseley Station.

Network Rail engineers began carrying out repairs on Tuesday and worked round the clock to remove the 80tonnes of debris from above the tunnel, including large trees.

Due to the challenging location of the incident, it wasn’t possible to remove the debris from above, so the debris was brought onto the track below and then removed. This meant overhead line equipment also had to be removed and reinstalled once all of the debris had been cleared. Network Rail also carried out work to clean and improve a public access road and track which will improve the area for the local community.

Chris Gee, head of operations for Network Rail, said: “Our engineers have done a fantastic job and have worked round the clock since Tuesday so that we could safely reopen the railway for passengers this morning.

“We’re sorry for anyone who was inconvenienced due to this incident and thank them for their patience whilst we carried out this vital work."

ENDS

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Amy Brenndorfer
Senior Communications Manager
07858375508
07730359569
Amy.Brenndorfer@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk