Network Rail completes vital project to improve two Grantham railway bridges: IMG-20210416-WA0010

Monday 19 Apr 2021

Network Rail completes vital project to improve two Grantham railway bridges

Region & Route:
Eastern

Network Rail has completed a £2.7million project to upgrade two railway bridges in Grantham which carry the busy East Coast Main Line.

The work to strengthen the bridges – spanning Barrowby Road and Springfield Road – will keep the railway running reliably and make sure people can pass safely underneath it for years to come.

Over the last seven months, Network Rail teams have carried out vital repairs to the steel and brickwork on the bridges, as well as re-waterproofing them and re-painting sections.

The work was carried out in stages to make sure one of the two roads could stay open for the vast majority of the project. The improvements to the railway bridge at Barrowby Road were completed in early December 2020, before work began at Springfield Road in January.

The wintry weather which hit the region in February caused some delays to the work, and Springfield Road fully reopens today (Friday 16th April).

Paul Rutter, Route Director for Network Rail’s East Coast route, said: “This vital work to strengthen the two railway bridges in Grantham means they are fit for purpose for the future - to carry the East Coast Main Line and for people in the community to safely pass underneath them.

“We carefully planned the project to minimise disruption for people in the community as much as possible. The weather brought some challenges and we want to thank drivers, residents and businesses in Grantham for their continued patience while the work was carried out.”

ENDS

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Greg Moulds
Media relations manager
Network Rail
greg.moulds@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk