Minister views progress as engineers reach half-way in £60m tunnel renewal: EGIP Queen Street station June 3 - Transport Minister Humza Yousaf

Friday 3 Jun 2016

Minister views progress as engineers reach half-way in £60m tunnel renewal

Region & Route:
Scotland’s Railway: Scotland

Engineers working to renew the railway in Glasgow Queen Street tunnel have completed the first line of track through the kilometre-long structure.

Transport Minister Humza Yousaf visited site today (Friday, June 3), to view progress on the £60m project – which is the biggest piece of engineering work on the Edinburgh-Glasgow railway since it was built in the 1840s.

Since the high level station closed to trains on March 20, over 2,100 engineers have invested more than 150,000 work hours to renew track through the tunnel and to lengthen and rebuild platforms and track layouts within the station.

With the 20-week scheme progressing to plan, the project team has now completed the first line of new slab-track and remains on course to reopen the high level station on August 8.

Work has now begun on laying the second line of new slab-track through the tunnel.

Over the last 10 weeks Network Rail engineers, who are renewing the tunnel for the ScotRail Alliance, have removed over 5,000 tonnes of concrete and rock, created a new 945m concrete base and installed 820m of new slab-track units and 2000m of new rail.

Transport Minister, Humza Yousaf, said: “Delivering any major infrastructure programme in a live rail environment is a challenging undertaking and the Queen Street tunnel is certainly no exception.

“This is a massive logistical operation by Network Rail that has seen over 150,000 hours worked to date and I am pleased to see it reach the halfway point on schedule.

“Whilst acknowledging the ongoing success of ScotRail’s communications and service alterations, which are keeping the public informed and keeping them moving, I would also like to thank rail passengers who are affected by these works for their ongoing patience and understanding.

“This work is literally paving the way for Scotland’s new fleet of electric trains, which will begin to be introduced in to service next year.”

David Dickson, ScotRail Alliance infrastructure director, added: “We have now passed the half-way point in this vital project and our engineers have completed a huge amount of work as they stay on course to reopen the tunnel for passengers on August 8.

“The renewal of the tunnel track, and the installation of overhead power equipment, will allow the introduction of faster, longer and greener trains on the main Edinburgh-Glasgow line – delivering thousands of extra seats, shorter journey times and improved accessibility for customers.

“Although, this is a massive engineering challenge it has been meticulously planned and we’d like to thank customers for their support and understanding while we deliver this investment in Scotland’s railway.”


The tunnel renewal is being delivered by engineers working on the Edinburgh Glasgow Improvement Programme (EGIP) to electrify the main Edinburgh-Glasgow line.

Through EGIP, 70 Hitachi Class 385 electric trains will be rolled out on a number of routes by December 2018. These will allow ScotRail to run trains of up to eight carriages on the main Edinburgh-Glasgow line once the new Glasgow Queen Street station is complete.

The Scottish Government’s investment in the redeveloped Glasgow Queen Street station, which is due to be completed in 2019, will see the station transformed into a modern facility with increased concourse space, improved accessibility and remodelled passenger facilities.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk