MIDNIGHT LIFT-OFF TAKES NEWPORT STATION TO NEW HEIGHTS: First lift-off for eco-friendly Newport station

Monday 5 Oct 2009

MIDNIGHT LIFT-OFF TAKES NEWPORT STATION TO NEW HEIGHTS

Region & Route:
| Wales & Western: Wales & Borders
| Wales & Western

As the year-long countdown for the Ryder Cup begins, work to build the new eco-friendly station at Newport is also gathering pace. 

The very first 'lift-off' for this scheme has been successfully completed, and today the Newport station area sees a slightly different skyline, with concrete and steel structures rising behind the site hoardings. 

In the small hours of Sunday morning, in less than seven hours, a total of 33 tonnes of concrete and steel beams were lifted into position. 

Mike Gallop, route enhancement manager, Network Rail, said: “Ten of thousands of people will benefit from the new £22m station.  The station will double in size with improved facilities and access for all. 

"Working overnight meant no impact on passengers and train services, while off-site pre-construction minimised the amount of time need to carry out this much work."

Arriva Trains Wales head of stations Peter Northcott said:  “We are beginning to see the new station take shape and there is no doubt that it will be a modern facility for our passengers when completed.  We are grateful to Network Rail and their contractors for completing this important stage with minimum disruption to our services and our passengers.”

To carry out the work a huge 500-tonne road crane, which can stretch as far as 40 metres, was used to lift the new structures into place. The two concrete rings and a steel ring beam stand at a combined height of five metres and form the central support column for the new station footbridge.

Since work has started, engineers have been working round the clock to complete vital ground work, including piling, excavating and building concrete foundations.

In the next couple of months, work will be focused on creating a new road junction on the south side, constructing concrete foundations for the station buildings and installing the new passenger footbridge.

The Newport station regeneration scheme is jointly funded by Network Rail and the Welsh Assembly Government.

The new station will become the greenest and is the biggest station project to be carried out in south Wales. 

Notes to editors

- Measuring 2,100 square metres, the new Newport station will be nearly twice the size of the old station and will be built with a special sustainable material - ethylene tetra fluoro ethylene - also extensively used by the Eden Project.

- Passengers will benefit from two new terminals and an additional new entrance to serve passengers from the northern side of the city. A station footbridge will conveniently connect passengers to all platforms

- The station will also be equipped with three lifts, CCTV, modernised customer information system and new waiting shelters. Both terminals will also have improved ticketing and information points and more shops

- There will also be a new and expanded car park with 250 spaces and platform 4 will also be extended by 50 metres to be able to accommodate longer trains

- ETFE is a recyclable material that is extremely lightweight and compared to glass, requires significantly less steel to support the structure.  The material also provides better insulation than double glazing thus requiring less energy to heat the internal space

- ETFE does not degrade under UV light or atmospheric pollution and its unique non-stick, self-cleaning design means that grime can be easily removed by rain.  ETFE does not pose any threat to the ozone layer and was originally designed for the space industry.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail