Major works for Crossrail project delivered by Network Rail over bank holiday weekend: New track delivered at Westbourne Park - May 16 235964

Wednesday 4 May 2016

Major works for Crossrail project delivered by Network Rail over bank holiday weekend

Region & Route:
National
  • £14.5m package of work carried out at 21 different locations to prepare tracks, infrastructure and stations for new railway that will be known as the Elizabeth line
  • Network Rail works around the clock as part of huge programme of works
  • A selection of images of the early May bank holiday works is available to download from the image library

Network Rail continued its massive programme of works on the Crossrail project over the May bank holiday weekend with 1,800 people working around the clock to deliver important upgrades to the railway.

With three quarters of the route – which will be known as the Elizabeth line from 2018 – running above ground, Network Rail’s work is vital as it will link the new tunnels built by the Crossrail project beneath London with the existing rail network and allow people to travel from Reading and Heathrow right through the capital to Shenfield in Essex and Abbey Wood in the London Borough of Greenwich without changing trains.

Network Rail’s programme of early May bank holiday work included: 

  • West of London, between Paddington and Reading:
    • Track remodeling work, electrification and signalling commissioning at Old Oak Common to create space for the new Elizabeth line tracks.
    • Track remodeling work, electrification and signalling commissioning at Southall and Hayes & Harlington to make way for new bigger stations and longer platforms.
    • At West Ealing and Slough, station works included platform extensions and canopy cutbacks to accommodate the overhead electrical lines needed for the Elizabeth line trains.
    • Construction of the new Heathrow flyover at Stockley junction also progressed with 25 huge concrete sections lifted into place that form part of a new ramp. The new flyover will allow more trains to run more reliably and doubles the capacity to and from Heathrow.
    • Electrification works between Stockley and Maidenhead to support new electric trains.
  • East of London on the Great Eastern Main Line section of the route, work continued apace in preparation for the new trains:
    • Significant electrification upgrade work continued at Shenfield.
    • Platform extension and bridge works were carried out at five stations (Goodmayes, Gidea Park, Harold Wood, Brentwood and Shenfield) in order to accommodate the longer trains that will operate on the Elizabeth line and ensure the stations are step free.
    • The landmark new station at Abbey Wood is now taking shape with huge concrete beams lifted into place to form the base of the new two storey building. Plus 600m of track was also renewed over the bank holiday weekend.

Matthew Steele, Crossrail Programme Director at Network Rail, said: “I would like to thank passengers and our lineside neighbours for their patience over the bank holiday whilst we carried out these major works. There is never a good time to close the railway but with far fewer people travelling over the long weekend, we had a good opportunity to deliver these vital improvements. With meticulous planning along with the hard work and dedication of our team and contractors, we have once again delivered a lot of complex work and taken a big step towards making the Elizabeth line a reality.”

Matthew White, Surface Director at Crossrail said: “The Crossrail project will provide a step change in public transport for many thousands of people in outer London, Berkshire and Essex. The programme of work delivered by Network Rail over the May Bank Holiday was a vital part of preparing the existing rail network for the arrival of the new Elizabeth line services.”

Key facts and figures

  • £14.5m programme of work
  • 21 different sites on the route across Berkshire, west London, Essex and Kent
  • 54,000 hours worked by 1,800 people
  • 28 engineering trains used
  • 3 Kirow cranes used, 8 road cranes including 1 x 500 tonne crane at Stockley
  • Over 1.5km of track renewed or moved
  • 4 new sets of points installed
  • 6 platforms extended or upgraded to accommodate new, longer Elizabeth line trains

Ends

For further information contact Richard Griffiths, Head of Communications – Crossrail, Network on 07734 649189 or email Richard.griffiths@networkrail.co.uk or the Crossrail Press Office on 020 3229 9552 or email pressoffice@crossrail.co.uk

About Crossrail and Network Rail:

Network Rail is a key partner in delivering the Crossrail project. It is responsible for the design, development and delivery of the parts of the route that are on the existing rail network in outer London, Berkshire, Bucks and Essex. Network Rail’s work, which will integrate the new rail tunnels beneath London with the existing rail network, includes upgrades to track, major civil engineering projects, new overhead electrification equipment and improvements to stations and bridges.

The route will pass through 40 stations from Reading and Heathrow in the west, through new twin-bore 21 km tunnels to Shenfield and Abbey Wood in the east. The Transport for London (TfL) run railway will be named the Elizabeth line when services through central London open in December 2018. The Crossrail project is being delivered by Crossrail Limited, a wholly owned subsidiary of TfL, and is jointly sponsored by the Department for Transport and TfL.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Dan Donovan
Media Relations Manager
020 3356 8700
Dan.Donovan@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk