Friday 24 Jan 2020
Major track upgrade for Norwich to London rail passengers begins this weekend
- Region & Route:
- Eastern: Anglia
Network Rail will be working at Maryland on the main line from Norwich to London this weekend to renew track which will result in fewer delays and increased reliability.
Over a total of nine weekends, engineers will carry out the following work:
- replace track and points at Maryland to improve punctuality and reliability
- overhead wire power upgrades for new trains
- work at Ilford to improve drainage
Over time, track becomes worn from constant use, especially at this key junction on the busy main line, and needs to be replaced to keep services on the move to improve reliability.
Ellie Burrows, Network Rail’s route director for Anglia, said: “This is a very busy section of the network which sees hundreds of trains every day that our passengers rely on. This work will help us to maintain a safer and more reliable railway for passengers by reducing the number of train services affected by delays and cancellations.”
Jamie Burles, Greater Anglia managing director said: “We are very sorry about the inconvenience these works cause to passengers. We will make sure that all customers can complete their journey, even if part of it is by bus.
“This work is essential so that, together with Network Rail, we can improve punctuality and reliability on our railway.”
A rail replacement service will run while the work takes place.
Notes to editors
The rail replacement service will be in place between Ingatestone and Newbury Park for the Central line on the following weekends:
25 – 26 January
15 – 16 February
22 – 23 February
29 February – 1 March
7 – 8 March
14 – 15 March
21 – 22 March
28 – 29 March
18 – 19 April
More details can be found at www.greateranglia.co.uk
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk