Major Stirling-Alloa upgrade work set to begin: Overhead wires on Edinburgh-Glasgow route

Wednesday 14 Mar 2018

Major Stirling-Alloa upgrade work set to begin

Region & Route:
Scotland’s Railway: Scotland

Engineers will be working around-the-clock for the next four weeks to deliver a multi-million-pound upgrade to prepare the Alloa line for electrification.

Hundreds of engineers will work over 16,000 hours as they install the overhead power equipment needed to introduce electric services on the route – delivering more seats for customers on quieter, greener trains.

The work, which is part of a Scottish Government-funded programme to electrify lines throughout the central belt, will take place from Saturday, March 17, until Monday, April 16.

A replacement bus service will operate between Alloa and Stirling during this period to help minimise disruption for passengers while we deliver this vital investment in Scotland’s railway.

Over the four weeks, engineers will be working from Stirling to Alloa along the six miles of the route, installing 261 masts, and supporting cantilevers, and stringing overhead power cables.

The project is part of the wider programme to electrify the lines linking Stirling, Alloa and Dunblane to Glasgow and Edinburgh.

Once complete, the electrification of the Stirling-Dunblane-Alloa lines will mean:

  • Many services will be operated by electric class 385 trains, which will offer a better experience and reduce some journey times from Stirling to Glasgow and Edinburgh.
  • More seats on services between Alloa, Dunblane, Bridge of Allan, Stirling and Edinburgh.
  • Less noise and better air quality for those who live and work near the railway.

Paul Reilly, Network Rail programme manager, said: “Electrification will transform travel across the central belt of Scotland and is part of our commitment to delivering the best railway Scotland has ever had.

“Our engineers will be working around-the-clock to complete this complex programme as quickly as possible.

“We understand the inconvenience these works will cause to some passengers and residents and we are working hard to keep disruption to a minimum.

“We are encouraging customers to leave extra time for travel, and plan journeys in advance. All train and bus times are available at www.scotrail.co.uk/alloaworks as well as on the ScotRail app.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk