Major section of Chiltern main line secured from landslips: Harbury embankment aerial view 16x9

Tuesday 16 Mar 2021

Major section of Chiltern main line secured from landslips

Region & Route:
North West & Central
| North West & Central: Central

Earth beside the Chiltern main line in Warwickshire has been secured from landslips to provide more reliable journeys for passengers.

Network Rail engineers stabilised a slope on the south side of Harbury tunnel between Leamington Spa and Banbury as part of a £9m investment.

The major improvements started in December 2019 and workers left the site on March 5.

From start to finish the major earth moving project work took 15 months to carry out.

The underground conditions in the area have caused problems for the railway ever since it was built in 1852*.

Most recently in 2015, 300,000 tonnes of earth moved on the north side of Harbury tunnel forcing the important passenger and freight railway route between the Midlands and London to close for six weeks.

Emma Gray, scheme project manager at Network Rail, said: “This significant investment to secure this part of the Chiltern main line will ensure reliable journeys for passengers between Birmingham and London for many decades to come.

“The ground here, made up of layers of limestone and shale, can be unstable and could potentially cause issues for the railway running through it. This preventative work will stop future slips and make it much more secure.

“We know Harbury very well after the huge landslip in 2015 and I want to thank the local community for their patience while we carried out this important work to protect the railway.”

Large nails and piles have been dug into the slopes beside the tracks to make them stronger.

A new retaining wall has also been built at the bottom of the railway cutting to prevent soil movement.

The project has been carried out during the daytime while passenger and freight trains continued to run below, meaning no disruption to services and no noisy overnight work.

Eleni Jordan, commercial & customer strategy director for Chiltern Railways, said: “The work that Network Rail have carried out at Harbury will ensure that we can continue to run reliable and punctual services for our customers for many years to come.”

For more information on how Network Rail carries out this type of work visit www.networkrail.co.uk/earthworks-cutting-slopes-and-embankments.

Notes to Editors

*The first attempt to make the slopes of the cutting at Harbury shallower to prevent landslips was undertaken by Victorian engineers of Great Western Railway in 1884.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk