Major repairs to Royal Border Bridge throughout 2022 – community invited to learn more: Royal Border Bridge - Invite to information event-2

Thursday 20 Jan 2022

Major repairs to Royal Border Bridge throughout 2022 – community invited to learn more

Region & Route:
Eastern
| Eastern: East Coast

The iconic Royal Border Bridge in Northumberland will be repaired throughout 2022 in a major project led by Network Rail.

Work on the scheme began earlier this month and will run until November 2022. During this time, engineers will repair all 28 arches of the Grade I listed bridge, which sits across the River Tweed.

Carefully planned structural repairs should mean that the bridge won’t require any major maintenance work for the next 30 years, allowing the landmark to be enjoyed for years to come without impacting the community.

Network Rail is holding an online information event on Thursday 27 January from 18:00 to 19:00, where members of the project team will be on hand to explain the work in more detail and answer any questions residents may have. Those wishing to join should visit https://bit.ly/31YwsNn as the event starts.

Site facilities, scaffolding and a rope access system will all be installed during the work. This is vital to allow teams to work safely. The footpath along the bridge will also remain open throughout to minimise the impact on the community.

Sarah Reid, Route Director for Network Rail’s East Coast route, said: “In this feat of engineering, we’ll be repairing the iconic Royal Border Bridge so that it can continue to transport passengers between England and Scotland along the East Coast Main Line – and crucially, be enjoyed by the community – for years to come.

“I know this is a well-loved landmark, so I’d encourage anyone who wants to find out more about our work to come along to the online information event and ask any questions they have.”

ENDS

Notes to Editors

To find out more about the history of the Royal Border Bridge, visit The history of the Royal Border Bridge, Berwick - Network Rail

Timeline of work

  • Jan 2022 – Compound set up and brickwork repairs to arches 1 – 2
  • Feb 2022 – Brickwork repairs to arches 3-5
  • March 2022 – Brickwork repairs to arches 4-7
  • April 2022 – Brickwork repairs to arches 8-11
  • May 2022 – Brickwork repairs to arches 12-15
  • June 2022 – Brickwork repairs to arches 16-19
  • July 2022 – Brickwork repairs to arches 20-21
  • August 2022 – Brickwork repairs to arches 22-25
  • Sept 2022 – Brickwork repairs to arches 26-28
  • Oct 2022 – Further repairs to various arches
  • Nov 2022 – Remove site compound

Working hours

  • Monday - Friday 09:00-18:00
  • Saturday 22:00-08:00

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Louise Leighton
Media Relations Manager
Network Rail
07858 375508
louise.leighton2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk