Huddersfield station will be closed following the last train service on Thursday 24 December 2026 until Sunday 31 January 2027, while extensive upgrades are completed as part of the Transpennine Route Upgrade (TRU).
When Huddersfield station reopens on 1 February, customers will be able to use the newly rebuilt and extended platforms 4, 5 and 6 for the first time. The longer platforms will provide more space for customers while creating the capacity needed for longer trains with more seats. New waiting areas and the completion of the station's historic roof canopy restoration will further enhance the station environment, providing improved shelter while preserving the station's heritage.
Alongside these station improvements, major railway infrastructure upgrades, including a new track alignment through the station, will increase network capacity and lay the foundations for more frequent, faster and more reliable services in the future.
Work will also progress on wider improvements across the route during this period. This includes upgrades at Deighton station, the installation of overhead line equipment to support future electrification, new track to support future capacity and service improvements, and track and drainage renewals in the Stalybridge area to increase journey reliability.
During the closure, no trains will be able to run through Huddersfield station with diversionary routes and rail replacement buses in operation to keep customers on the move. Brighouse station will be a key road-rail interchange point for customers travelling to and from Huddersfield during this period.
Sophie Leishman, TRU Sponsor, said: "This closure will mark a major milestone for the Transpennine Route Upgrade, delivering significant improvements to Huddersfield station while laying the foundations for future benefits across the route.
“When the station reopens, customers will see the benefits of new platforms and enhanced facilities, alongside major railway infrastructure improvements that will support future benefits for those travelling across the North.
“We are grateful to customers and local communities for their continued patience and support while we deliver these vital upgrades."
Carl Harland, TRU Customer Lead at Northern, said: “While extensive works are taking place at Huddersfield station, we will once again be using the car park at Brighouse station as a rail-road interchange to help keep customers on the move.
“We advise all customers to thoroughly check the details of their journey before they travel, as their journey may be subject to an amended timetable, a diversionary route, or may be replaced in part or whole by bus.
“We would like to thank our customers, especially those who travel through Huddersfield regularly, for their continued patience while these transformational works are undertaken at the station.”
Some further enhancements at Huddersfield station will continue from February onwards, including the completion of the historic tearoom restoration, the refurbishment of the platform 2 toilets and additional upgrades to customer facilities, while wider railway improvements across the TRU route continue to be delivered.
Notes to Editors
Huddersfield station will be closed following the last train service on Thursday 24 December 2026 until Sunday 31 January 2027, reopening on Monday 1 February. A breakdown of services changes during this period can be found below:
25-26 December 2026: railway closed for national Christmas shutdown.
27 December 2026 – 1 February 2027:
- Mossley, Greenfield, Marsden, Slaithwaite, and Huddersfield stations will not be served by rail services.
- Customers will primarily interchange between services/modes at Stalybridge and Brighouse. Lockwood and Wakefield Kirkgate also act as key rail/road interchange locations.
- Replacement buses in operation include:
- o Huddersfield <> Brighouse (every 15 mins)
- o Huddersfield <> Stalybridge (direct, hourly)
- o Huddersfield <> Stalybridge (all stops, hourly – with additional peak time services)
- o Huddersfield <> Lockwood (every hour)
- o Brighouse <> Manchester Airport (every hour)
- o Huddersfield <> Wakefield Kirkgate (Peak-time only, weekdays)
- o Marsden to Brighouse (peak-time only, weekday morning peak time service)
- o Brighouse to Marsden (peak-time only, weekday evening peak time service)
Sunday 31 January 2027 until 16:25:
- Mossley, Greenfield, Marsden, Slaithwaite, Huddersfield, Mirfield and Brighouse stations will not be served by rail services.
- Customers will primarily interchange between services/modes at Stalybridge and Dewsbury. Penistone and Halifax also acts as key rail/road interchange locations.
- Replacement buses in operation include:
- o Huddersfield <> Stalybridge (hourly, fast & stopping)
- o Huddersfield <> Leeds (every 30 minutes, direct)
- o Huddersfield <> Dewsbury (hourly, direct)
- o Huddersfield <> Dewsbury (hourly, stopping)
- o Halifax <> Dewsbury (hourly, stopping)
- o Huddersfield <> Penistone (every hour)
- o Halifax/Brighouse <> Wakefield Kirkgate (stopping)
Brighouse station car park will be closed from Tuesday 22 December until Monday 1 February 2027, reopening on Tuesday 2 February, to facilitate rail replacement bus services to and from Huddersfield. While Brighouse station car park is closed, alternative parking will be available at nearby public facilities such as Daisy Street pay and display car park, operated by Calderdale Council. Blue badge holders will continue to have access to designated spaces in the station car park.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Chantele Hodson
Communications Manager
chantele.hodson@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk