Major engineering work delivered at Glasgow Central during emergency closure: Glasgow Central station work-3

Monday 23 Mar 2026

Major engineering work delivered at Glasgow Central during emergency closure

Region & Route:
Scotland’s Railway: Scotland

Network Rail engineers seized the rare opportunity of the closure of Scotland’s busiest station to deliver an extensive package of maintenance and renewals that would ordinarily have taken around ten months to complete.

With Glasgow Central closed from March 8 due to the Union Street fire, teams moved quickly to plan and carry out a broad range of essential works before the station partially reopened on March 18.

The work would’ve normally required multiple weekend and weekday nightshifts to complete around passenger services at Central, where over 1,200 trains move in and out each day.

On the tracks more than 108 tonnes of used rail were removed from the station approaches along with 73 old timber sleepers. More than 6,200 sqm of vegetation was also cleared.

Engineers carried out extensive maintenance on Overhead Line Equipment (OLE) around the station, inspecting 299 sections and carrying out a range of repairs to the wires, insulators and other kit.

Work was carried out on switches and crossings (pieces of track that move trains from one line to another) and inspections made on 439 insulated block joints (part of the signalling system that pinpoints where trains are on the tracks).

Keiren Sharkey, infrastructure maintenance delivery manager at Network Rail, said: “It was a situation none of us expected, but our teams reacted immediately and were determined to make the most of this rare opportunity.

"It allowed teams based in Motherwell and Glasgow to complete an enormous amount of work that would have required a much longer period of time to complete under normal conditions.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail Press Office - Beth Franklin
Media Relations Manager
Network Rail
07710221337
Beth.Franklin@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk