Line to reopen: Engineers have repaired the 10-metre Lingfield landslip, which closed the railway between Hurst Green and East Grinstead, Surrey: Lingfield landslip-4

Monday 23 Jan 2023

Line to reopen: Engineers have repaired the 10-metre Lingfield landslip, which closed the railway between Hurst Green and East Grinstead, Surrey

Region & Route:
Southern
| Southern: Sussex

Passengers are being reminded to check before they travel tomorrow as the line between Hurst Green and East Grinstead is set to reopen tomorrow morning.

Network Rail engineers and contractors BAM Nuttall have worked around the clock to repair a landslip that closed the railway between East Grinstead and Hurst Green in Surrey, on Tuesday, January 17.

The line had to be blocked after a 10-metre stretch of a 7-metre- high embankment slipped away from the railway, around half a mile towards London from Lingfield station*. In addition, cracks spread six metres on either side of the slip site, leading to fears it could get worse if action wasn’t taken immediately.

Engineers installed a steel wall, made of 44, 10-metre-long steel piles, which will stabilise and support the embankment, using 50,000 tonnes of ballast, the stone that supports the track.

Before the line can fully reopen for passengers commuting tomorrow morning, a tamper train will be used to compact the ballast and make sure the newly laid track is properly aligned, while engineers relay power and signalling cables.

Network Rail’s route director for Sussex, Lucy McAuliffe, said: “I’m really pleased to say that we’re able to reopen the railway slightly earlier than expected ahead of our midweek target.

“Our teams and contractors have been working really hard to get the landslip fixed as quickly as possible and I’d like to say a huge thank you for their quick response and collaborative efforts.

“I’d like to thank our neighbours living alongside the railway for their patience whilst we carried out this crucial work and those passengers who were faced with more disruption last week. We are more than confident that the railway will be reopened from tomorrow morning but in the meantime please continue to check before you travel to be on the safe side."

Jenny Saunders, customer services director for Southern and Thameslink, said: "On behalf of our passengers we're grateful to Network Rail and their specialist engineers for making the line safe again so quickly after the landslip brought on by last week's heavy rain. Thanks also to our passengers for bearing with the alternative travel arrangements while this vital work was completed."

Notes to Editors

On landslips:

In the Southern region, we’ve suffered more than 200 earthworks failures in the past three years alone, and 25 of those have resulted in big line closures that have disrupted passengers. They’re becoming more and more frequent due to climate change. The Met Office says the UK has suffered 7 of its 10 wettest years on record since 1998, and more rain means more landslips…

The Southern Region looks after earthworks that if joined together would stretch all the way from Lands End to John O Groats. We have a £500 million-pound five-year budget to look after those earthworks. To rebuild or strengthen all of our earthworks would cost billions of pounds and close stretches of railway for very long periods. So, we focus on examinations so we know where to repair and mitigate, carry out regular drainage inspections and maintenance so the water can flow away and reduce the risk of landslips, and in some locations install electronic devices into the ground (remote condition monitoring) which monitor movement and send alerts if there is a landslip so we can close the line and keep passenger safe.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Tala Ghannam
Media Relations Manager (Campaigns) - National
Network Rail
07548 108907
tala.ghannam2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk