Levenmouth Rail Link active travel bridge installation plan revealed: IMG 0188

Tuesday 3 Sep 2024

Levenmouth Rail Link active travel bridge installation plan revealed

Region & Route:
Scotland’s Railway: Scotland

Methilhill and Cameron Bridge will have a new active travel bridge to connect the communities later this month.

Network Rail will crane the 129-metre structure into position over the next fortnight, connecting the various active travel paths under construction as part of the Levenmouth Rail Link project.

That work is taking place from 2 to 16 September, with nine pre-fabricated sections, including bridge piers, staircase sections and four spans of bridge-deck being installed.

The installation had originally been planned ahead of the opening of the rail link but was delayed due to the company building the bridge going into administration this year.

Complex discussions with the administrator to release the part-built structure, as well as the need to source a new supplier, compounded that delay.

Now, with plans in place to complete the work, no parking and no waiting zones have been introduced on Poplar Road and Kirkland Walk until 16 September so that work vehicles can access the site.

Tommy McPake, senior programme manager, Network Rail said: “The team has worked hard to build the alternative walking route and then to deliver on the revised timeline to get the structure complete and site prepared for the bridge installation.

“While it was disappointing not to have the bridge in place ahead of the opening, it was due to circumstances beyond our control that could not have been foreseen.

“We hope the new bridge allows the community in Methilhill the opportunity to fully join in the excitement the return of the passenger service to Levenmouth has created. We’re now very close to completing the connection to their local station which will enable them to easily access all of the opportunities the railway delivers.

“It is always exciting to see the crane lift the bridge into position to create what will be a very impressive looking structure that will support active travel in the area.

“We are grateful to the surrounding communities for their cooperation as we bring the bridge sections to site and look forward to completing the work in the coming weeks.”

The bridge will be craned into position using a 750-tonne crane. 

At its highest the bridge will sit approximately 8m above the river and will drop in height as it crosses the railway to connect into Cameron Bridge station.

Notes to Editors

Work on the foundations and approaches to the Methilhill bridge is underway.

The bridge is a 129m active travel bridge spanning the River Leven from Methilhill and landing at Cameron Bridge station.

It consists of a 60m span over the River Leven and 4 spans over lower ground ranging between 14.4m to 22.5m in length.

Work to deliver an alternative walking route to connect from Methilhill to Cameron Bridge station (via the A915 river bridge) was delivered in late May.

The bridge at Methilhill will be the second of two structures delivered as part of the Levenmouth Rail Link project following successful completion of the bridge at Duniface ahead of the railway opening.

A third structure at Mountfleurie will be delivered in 2025 on behalf of Fife Council following final design specification being agreed and subject to planning approval. 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk