Leven bridge is coming down: BawbeeBridgesurfacePlaning

Tuesday 16 May 2023

Leven bridge is coming down

Region & Route:
Scotland’s Railway: Scotland

Preparatory work ahead of the demolition of the rail section of the River Leven (Bawbee) bridge is now underway.

Network Rail is replacing the abutments and deck of the road bridge which is suffering from significant deterioration and showing signs of chlorine contamination and corrosion.  The work is to remove a long-standing weight restriction from the structure.

The work on the bridge, which sits above the site of the new Leven station, is funded by Fife Council and is being delivered on their behalf by Network Rail as part of the Levenmouth Rail Link programme.

With the road now closed to both road traffic and pedestrians, the area has been fenced-off to protect the community from coming into contact with machinery carrying out the work.

Street-furniture – road signs, lamp posts etc – is being removed before the existing road surface will be lifted and the bridge parapets (side walls) removed. 

It is anticipated that the actual demolition of the structure itself will be from Friday May 19 with the work complete by the end of the month. The start of work on the replacement structure will immediately follow.

The temporary footbridge adjacent to the Bawbee bridge will also be closed during this time. Access across the river will be via the footbridge across the temporary road bridge which was recently opened.

Sean Clemie, project manager for bridge works, said: “With the temporary road bridge in place to maintain access across the river, we can now focus on the main task – demolition and reconstruction of the Bawbee bridge.

“Obviously, with the main element of the work underway, we have fenced off the bridge and the adjacent temporary structure will also be out of use during the demolition for safety reasons.

“We will prepare the structure for demolition at the weekend and after the debris has been cleared, we will immediately start work on the construction of the new bridge. From then we will enable reinstatement of the utilities - essentially putting everything that is needed back on the bridge.”

For more information you can also visit the Levenmouth project page at www.ScotlandsRailway.com and for the latest updates follow on twitter @NetworkRailScot

Any questions about the work can be emailed to LevenmouthRailLink@networkrail.co.uk

Notes to Editors

Notes to Editors

The temporary road-bridge over the River Leven will support circa 18,000 vehicle movements per day during major work to demolish the structure.

The diversion route takes traffic from the A955/B933 roundabout, through the leisure centre car park and across the river via the temporary bridge. Traffic joins the existing road network at the new roundabout that has been constructed on South Street (B932).

Key dates for the work to replace the Leven (Bawbee) bridge:

  • Start of temporary road construction – March 2023
  • Temporary road in use – early May 2023
  • Bridge demolition – May 2023
  • Leven Bridge renewal works – May-December 2023
  • Road reopened under traffic management – December 2023
  • Removal of temporary road bridge – January 2024
  • Road fully reopened – February 2024.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk