Level crossing in Cheltenham to close for emergency works until April 2021: Swindon Road for web

Tuesday 22 Dec 2020

Level crossing in Cheltenham to close for emergency works until April 2021

Region & Route:
Wales & Western

Network Rail has had to close the level crossing on Brockhampton Lane until 7 April 2021 to undertake vital works.

The level crossing was closed on Friday and will now remain closed until next April to allow Network Rail engineers to carry out essential repair work on the equipment that controls the level crossing.

The scale of work was originally expected to only result in the level crossing closing over two weekends, however, the most recent inspection has revealed that the condition of the wiring that controls the level crossing barriers has unexpectedly deteriorated.

As a result of this essential work, the level crossing will remain closed 24/7 to both pedestrians and vehicles until 7 April, subject to authorisation from the local highways authority.

A signed diversion route for vehicles has been put in place via Hyde Lane and letters have been sent to local residents providing further details of this work including a map of the diversion route.

Network Rail project manager, Spencer Hobbs, said: “We recognise this is a lengthy closure and are sorry for any inconvenience this emergency closure may cause the community.

“The safety of our passengers and crossing users is of the utmost importance to us so we have taken the difficult decision to fully close the crossing whilst we undertake this vital repair work.

“We are aware of instances of trespassing on level crossings and urge people to not put their lives at risk by attempting to cross the railway line while the crossing is closed. Trespassing on the railway is illegal and dangerous and we urge people to follow the diversions that have been put in place.

“We would like to sincerely thank everyone for their patience and understanding during this time.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Rob Breckon
Senior Communications Manager - Southern
Network Rail
07395 390759
rob.breckon@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk