Kew railway bridge track works completed to help minimise London Overground and District line delays: New wheel timbers in place on Kew railway bridge

Thursday 10 Oct 2024

Kew railway bridge track works completed to help minimise London Overground and District line delays

Region & Route:
Eastern: Anglia

Network Rail has completed track works on a Grade II listed bridge over the River Thames between Kew Gardens and Gunnersbury stations.

Over four weekends in September and October, the project team replaced all of the bridge’s 577 wheel timbers, which are used to hold the rails in place on both lines. Engineers also replaced worn-out rail at either end of the structure.

The old wheel timbers were over 25 years old and in poor condition, which meant there was a higher chance of track faults which cause delays for passengers. The replacement wheel timbers are made from a more durable material so they last longer and need less maintenance.

Kew railway bridge carries both London Overground’s Richmond – Stratford line and the District line. It is located on an intensively used stretch of route that has seen an increase in disruption in recent weeks, with Network Rail and Transport for London working together to drive down delays. Equipment that is causing multiple problems has been identified and a plan has been put into action to carry out repairs. Work is underway to improve both the management of the train service and the speed at which infrastructure problems are resolved.

At the same time as the works on Kew railway bridge, Network Rail took the opportunity to cut back vegetation along the line to help keep services running safely and reliably. In addition, engineers replaced points at Gunnersbury and completed a range of track works at Richmond, including replacing points, rails, wooden timbers and track circuit equipment.

Simon Milburn, Network Rail Anglia infrastructure director, said: “Replacing the deteriorating wheel timbers on Kew railway bridge will help us to keep this wonderful heritage structure operating as a key part of these busy railway lines. This was a vital job that really needed doing, and I’d like to thank London Overground and District line passengers for bearing with us while we delivered the project.”

Notes to Editors

Passengers should check for other planned engineering works on the London Overground and District line at tfl.gov.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Richard Cooper
Communications manager
Network Rail
0330 8577 132
richard.cooper3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk