Keeping track: progress update on Broxbourne bridge replacement: Concrete work on the central part of the bridge

Thursday 6 Apr 2023

Keeping track: progress update on Broxbourne bridge replacement

Region & Route:
Eastern: Anglia

Network Rail’s bridge replacement project in Broxbourne is moving closer to completion.

The Nazeing New Road bridge sits over the main line between London, Hertfordshire, Essex and Cambridgeshire. It needed to be fully replaced to keep everyone safe as the old structure had reached the end of its useful life.

The new bridge is designed to serve road users and rail passengers for 120 years.

Major work began in early January, requiring the road over the bridge to be closed. A diversion route for all motorists, pedestrians and cyclists remains in place.

Later in January, trains couldn’t run under the bridge for six days while the road was dug out, the old bridge lifted away and the new structure put in.

Since then, significant progress has been made. Engineers from Network Rail’s contractor, J Murphy & Sons, have been:

  • pouring, curing and waterproofing the new concrete bridge deck
  • strengthening the stretches of the bridge that were not fully replaced, helping to avoid the need for additional significant work in future
  • cleaning and painting the stretches of the bridge that were not fully replaced
  • enabling the reinstallation of gas, electricity and telecoms connections across the bridge

Further strengthening work is ongoing, with the bridge deck, road surface and pavement also due to be completed over the coming weeks.

Network Rail remains on target to reopen the bridge on Sunday 30 April. However, the complexity of the project means the programme is tight and unforeseen circumstances such as bad weather could mean it’s delayed by up to a week. Engineers are confident that the road will be re-opened by Sunday 7 May at the latest.

Simon Milburn, Network Rail’s infrastructure director for Anglia, said: “We’ve been making the very most of the road closure to deliver a replacement bridge that will serve Broxbourne and the railway for many decades to come. We’re really sorry for the impact on residents and road users, but not doing this work could have led to a prolonged short-notice closure that may have been even more disruptive.

“I’d also like to thank Greater Anglia passengers again for bearing with us while train services were affected for six straight days in January. We know this caused inconvenience for people on their journeys but the new bridge is vital for the future safe and reliable running of the line”.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Richard Cooper
Communications manager
Network Rail
richard.cooper3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk