Investment in more reliable Great Eastern main line continues into the New Year: Track renewal  London Anglia

Tuesday 17 Nov 2026

Investment in more reliable Great Eastern main line continues into the New Year

Region & Route:
Eastern: Anglia

Investment to improve reliability on one of the busiest rail routes into London will continue during weekends in January as engineers complete follow-up work on major track renewals carried out over Christmas.

Engineers will continue their crucial work in the new year to keep train services running smoothly and safely on the Great Eastern main line. The critical track infrastructure planned to be installed over Christmas at Forest Gate will continue to be the focus, to fully monitor and adjust eight new switches and crossings on this busy route into the capital, to make sure it settles safely and performs reliably for passengers.

New track and the ballast beneath naturally settle once trains begin running over it. Specialist tamping machines are used to restore the correct track alignment, helping to improve reliability, reduce wear and support smoother journeys for passengers.

Specialist treatment trains will also operate across the route during the New Year, carrying out activities including leaf removal, rail cleaning, track levelling, rail grinding and ballast tamping. Together, these works help reduce the impact of seasonal conditions, improve weather resilience and support a more reliable railway for passengers and freight customers.

These essential works will take place on selected weekends between early January and mid-February along the Great Eastern Main Line between Stratford and Chelmsford, on the London Overground Liberty Line between Romford and Upminster, and at specific times on the Southend Victoria and Southminster routes.

The planned engineering work includes:

  • Completing the adjustments of six new switches and crossings installed at Forest Gate.
  • Completing the adjustments of two new switches and crossings installed at Stratford station.
  • Renewing rails at Chadwell Heath.
  • Running specialist track treatment trains to improve seasonal resilience.
  • Refurbishing switches and crossings at Pudding Mill Lane.
  • Refurbishing switches and crossings at Shenfield.
  • Rerailing at Chadwell Heath, Brentwood, Rayleigh, Hockley 
  • Overhead line work between Romford and Chelmsford, and Wickford and Southminster. 
  • Drainage work at Seven Kings.

Engineers will also be carrying out routine maintenance across affected area and teams will be tackling vegetation between Forest Gate and Ilford.  Work will also take place at various stations including:

  • Roof refurbishment work at Forest Gate station.
  • Platform resurfacing at Manor Park station.
  • Demolition of a control room at Stratford station.
  • Repainting canopies at Shenfield.
  • Southminster and Hockley station canopy repairs.
  • Wickford station footbridge repair work.

Passengers travelling into the capital via Shenfield on weekends throughout January and early February are advised to check their journey before travelling and allow extra time where necessary.

Martin Beable, Chief Operating Officer for GBR Anglia said: “This planned engineering work is very important to help maintain the safe and reliable running of the railway, and we're using this time to make sure the critical pieces of infrastructure installed at Christmas are performing as expected.    

“Working with our partners, a rail replacement service will run while the works take place, and passengers are advised to check before they travel and allow more time for their journey.

“We would like to thank customers for their patience and understanding while this work is carried out.”

 

Travel Information for Greater Anglia customers

  • Saturday 9 January 2027
  • Saturday 16 January 2027

Greater Anglia services on the Great Eastern main line will not operate between Ingatestone and London Liverpool Street. Trains will continue to run between Norwich, Ipswich, Clacton and Shenfield, connecting into rail replacement buses at Ingatestone to Newbury Park for Central line services into Stratford and Liverpool Street station. 

Trains will continue to operate between Southend Victoria/Southminster and Shenfield, connecting into rail replacement buses at Shenfield to Newbury Park. 

  • Sunday 10 January 2027*
  • Sunday 17 January 2027*
  • Sunday 24 January 2027
  • Sunday 31 January 2027
  • Sunday 14 February 2027

Greater Anglia services on the Great Eastern main line will not operate between Beaulieu Park and London Liverpool Street. Trains will continue to run between Norwich, Ipswich, Clacton and Beaulieu Park, connecting into rail replacement buses to Newbury Park for Central line services. Greater Anglia customers' tickets will be accepted between Newbury Park and Stratford / Liverpool Street.

*On Sunday 10 and 17 January 2027 only, trains will continue to operate between Southend Victoria/Shenfield and Billericay connecting into rail replacement buses to Newbury Park. 

On Sunday 24 and Sunday 31 January and Sunday 14 February, buses will replace train services between Southend Victoria and London, connecting into Newbury Park for Central line services to Stratford/Liverpool Street. Buses will also replace trains between Southminster and Wickford, connecting into bus services to Newbury Park. 

Greater Anglia customers' tickets will be accepted between Newbury Park and Stratford / Liverpool Street on all dates listed above.

Travel Information for Elizabeth line and Liberty line customers

  • Saturday 9 January 2027 and Sunday 10 January 2027
  • Saturday 16 January 2027 and Sunday 17 January 2027
  • Sunday 24 January 2027
  • Sunday 31 January 2027
  • Sunday 14 February 2027

On dates listed above, Elizabeth line services will not operate between Liverpool Street National Rail station and Shenfield. A reduced Elizabeth line service between Paddington and Abbey Wood, calling at Liverpool Street Elizabeth line station and Whitechapel, will be running.

Rail replacement bus services will be available from Stratford, calling at all stations to Romford except Maryland. For the outer stations, passengers can change at Chadwell Heath for a bus beyond Romford including Gidea Park, Harold Wood, Brentwood and Shenfield.

Passengers can also take the Central line to Newbury Park underground station and transfer to a rail replacement bus service for Chadwell Heath and change to a bus for the outer stations.

On the dates listed above, London Overground Liberty line will not operate. Customers are advised to use local bus routes 165, 248 and 370.

Customers are advised to check before you travel on TfL’s Journey Planner or the TfL Go app.

Notes to Editors

  • Network Rail Anglia, Greater Anglia and c2c are working together as GBR Anglia, bringing track and train closer together to improve planning, strengthen day-to-day coordination and deliver a more joined-up railway for customers across the region.
  • Greater Anglia passengers can check their journey plans and service alterations via https://www.greateranglia.co.uk/travel-information/service-alterations
  • Elizabeth line and Liberty line passengers can check their journey plans at www.tfl.gov.uk/plan-a-journey

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail Anglia Press Desk - Stephen Deaville
Senior Communications Manager
Network Rail
0330 8577 132
07734647627
AngliaPressDesk@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk