Inverness line reopens after successful delivery of eleven-day programme: Train entering new double track section at Inverness airport station

Wednesday 26 Oct 2022

Inverness line reopens after successful delivery of eleven-day programme

Region & Route:
Scotland’s Railway: Scotland

The railway line between Inverness and Aberdeen reopened this morning following successful completion of eleven days of work on the Inverness Airport station programme.

Engineers worked around the clock to deliver extensive work between Inverness and Nairn as part of the wider programme of enhancements being delivered around the station development.

As well as work to significantly progress the new station, engineers delivered a 950m passing loop – effectively double-tracking through the station, installed three sets of points and renewed nearly 7km of rail adjacent to the site using 2.900 sleepers and 10,000 tonnes of ballast.

A new modular signalling system was also introduced through the area which saw the installation of 10 new signals and the first-use of ‘fibre’ cables for signalling.  In all more than 30km of signalling cable and 7km of power cable was run during the work.

The line closure also saw the completion of a new pedestrian access bridge which will enable the closure of the level crossing at Petty and the nearby pedestrian level crossing at Woodend. This will enhance both the safety of the railway

This work could not be delivered while the railway remained open and given the length of time required to complete specific elements, the activity has been scheduled for this time to minimise the disruption to the travelling public.

Billy McKay, Network Rail Scotland’s programme manager for the Inverness project said: “We are delighted that the work during the blockade has been successfully completed and that the line has been reopened for passengers.

“The volume of work delivered on site over the eleven-day programme meant planning and coordination was key and I am delighted that the work was carried out safely and efficiently is credit to the skill and expertise of the contractors involved.

“Thank you to passengers for their patience during this work and hope that they begin to see and experience the benefits the investment in the railway is delivering.”

For further information on the Inverness Airport station development visit www.scotlandsrailway.com/projects or email InvernessAirportStation@networkrail.co.uk

Notes to Editors

Over a period of 11 days from 23.55 Friday 14th October until the 04.45 on Wednesday 26th October, Network Rail and contractors worked day and night to deliver the work programmed during the closure of the line

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk